Question 76

Which of the following is not a process of project human resource management?

Options:

A.

Organizational Planning

B.

staff Acquisition

C.

Distribute Information

D.

Team Development

Discussion
Joey
I highly recommend Cramkey Dumps to anyone preparing for the certification exam. They have all the key information you need and the questions are very similar to what you'll see on the actual exam.
Dexter Jul 6, 2025
Agreed. It's definitely worth checking out if you're looking for a comprehensive and reliable study resource.
Faye
Yayyyy. I passed my exam. I think all students give these dumps a try.
Emmeline Jul 22, 2025
Definitely! I have no doubt new students will find them to be just as helpful as I did.
Teddie
yes, I passed my exam with wonderful score, Accurate and valid dumps.
Isla-Rose Jul 15, 2025
Absolutely! The questions in the dumps were almost identical to the ones that appeared in the actual exam. I was able to answer almost all of them correctly.
Madeleine
Passed my exam with my dream score…. Guys do give these dumps a try. They are authentic.
Ziggy Jul 9, 2025
That's really impressive. I think I might give Cramkey Dumps a try for my next certification exam.
Question 77

Completion of a product scope is measured against which of the following:

Options:

A.

WBS and WBS Dictionary

B.

Product Requirements

C.

Project Management Plan

D.

Product Management Plan

Discussion
Question 78

Which of the following relationships is rarely used in PDM (Precedence Diagramming Method)?

Options:

A.

Start-to-Finish

B.

Finish-to-Start

C.

Start-to-Start

D.

Finish-to-Finish

Discussion
Question 79

You are a project manager for your organization. Management has asked you to help them determine which projects should be selected for implementation. In a project selection model, which one of the following is the most important factor?

Options:

A.

Business needs

B.

Type of constraints

C.

Budget

D.

Schedule

Discussion