Question 84

A contingency plan is executed when _____________.

Options:

A.

A risks is identified

B.

An identified risk occurs

C.

When a workaround is needed

D.

Al1 of the above

Discussion
Question 85

Mathematical models using linear, dynamic, integer, or algorithm models are considered _____________.

Options:

A.

Project selection methods

B.

Project selection criteria

C.

A form of expert judgment

D.

A form of historical information

Discussion
Ayra
How these dumps are necessary for passing the certification exam?
Damian Oct 22, 2024
They give you a competitive edge and help you prepare better.
Melody
My experience with Cramkey was great! I was surprised to see that many of the questions in my exam appeared in the Cramkey dumps.
Colby Aug 17, 2024
Yes, In fact, I got a score of above 85%. And I attribute a lot of my success to Cramkey's dumps.
Faye
Yayyyy. I passed my exam. I think all students give these dumps a try.
Emmeline Sep 12, 2024
Definitely! I have no doubt new students will find them to be just as helpful as I did.
Kingsley
Do anyone guide my how these dumps would be helpful for new students like me?
Haris Sep 11, 2024
Absolutely! They are highly recommended for anyone looking to pass their certification exam. The dumps are easy to understand and follow, making it easier for you to study and retain the information.
Anya
I must say they're considered the best dumps available and the questions are very similar to what you'll see in the actual exam. Recommended!!!
Cassius Nov 2, 2024
Yes, they offer a 100% success guarantee. And many students who have used them have reported passing their exams with flying colors.
Question 86

A risk response which involves eliminating a threat is called ________.

Options:

A.

Mitigation

B.

Deflection

C.

Avoidance

D.

Transfer

Discussion
Question 87

Which of the following is not considered a cost of non-conformance to quality?

Options:

A.

Scrap

B.

Rework

C.

Expediting

D.

Process control

Discussion
Page: 21 / 27
Title
Questions
Posted

PMI-002
PDF

$36.75  $104.99

PMI-002 Testing Engine

$43.75  $124.99

PMI-002 PDF + Testing Engine

$57.75  $164.99