Question 80

Collocation can mean _______________.

Options:

A.

All, or almost all, team members are moved to a central physical location for the life of the project.

B.

Active team members may be at different physical locations, but meet on a regular basis.

C.

A war room is established where team members can meet periodically.

D.

Both A and c are correct.

Discussion
Billy
It was like deja vu! I was confident going into the exam because I had already seen those questions before.
Vincent Dec 21, 2025
Definitely. And the best part is, I passed! I feel like all that hard work and preparation paid off. Cramkey is the best resource for all students!!!
Aliza
I used these dumps for my recent certification exam and I can say with certainty that they're absolutely valid dumps. The questions were very similar to what came up in the actual exam.
Jakub Dec 3, 2025
That's great to hear. I am going to try them soon.
Honey
I highly recommend it. They made a big difference for me and I'm sure they'll help you too. Just make sure to use them wisely and not solely rely on them. They should be used as a supplement to your regular studies.
Antoni Dec 10, 2025
Good point. Thanks for the advice. I'll definitely keep that in mind.
Cody
I used Cramkey Dumps to prepare and a lot of the questions on the exam were exactly what I found in their study materials.
Eric Dec 2, 2025
Really? That's great to hear! I used Cramkey Dumps too and I had the same experience. The questions were almost identical.
Question 81

The concept of zero inventory is called ________.

Options:

A.

Six Sigma

B.

Continuous Improvement

C.

3ust in Time

D.

Zero Defects

Discussion
Question 82

Life cycle costing __________________.

Options:

A.

Includes acquisition, operating, and disposal costs when evaluating various alternatives

B.

Includes only the cost of the development or acquisition of a product or service

C.

Does not take into consideration the effect of project decisions on the cost of using the resulting product

D.

Botn B and c are correct

Discussion
Question 83

When Identify Risks should be performed?

Options:

A.

During Concept Phase

B.

During Development Phase

C.

During Implementation Phase

D.

Identify Risks should be performed on a regular basis throughout the project

Discussion