PMI Updated PMI-002 Exam Questions and Answers by casey

Page: 9 / 27

PMI PMI-002 Exam Overview :

Exam Name: Certified Associate in Project Management (CAPM) Certification
Exam Code: PMI-002 Dumps
Vendor: PMI Certification: CAPM
Questions: 748 Q&A's Shared By: casey
Question 36

Which of the following are inputs of the Develop Project Charter process?

Options:

A.

Project statement of work, Contract, Business case and organizational process assets

B.

Project SOW, project selection methods, and enterprise environmental factors

C.

Contract, project selection methods, enterprise environmental factors, and organizational process assets

D.

Contract, project SOW, enterprise environmental factors, and organizational process assets

Discussion
Cody
I used Cramkey Dumps to prepare and a lot of the questions on the exam were exactly what I found in their study materials.
Eric Apr 13, 2026
Really? That's great to hear! I used Cramkey Dumps too and I had the same experience. The questions were almost identical.
Zayaan
Successfully aced the exam… Thanks a lot for providing amazing Exam Dumps.
Harmony Apr 13, 2026
That's fantastic! I'm glad to hear that their dumps helped you. I also used them and found it accurate.
Freddy
I passed my exam with flying colors and I'm confident who will try it surely ace the exam.
Aleksander Apr 20, 2026
Thanks for the recommendation! I'll check it out.
Kingsley
Do anyone guide my how these dumps would be helpful for new students like me?
Haris Apr 5, 2026
Absolutely! They are highly recommended for anyone looking to pass their certification exam. The dumps are easy to understand and follow, making it easier for you to study and retain the information.
Question 37

You are project manager and working on gathering requirements and estimating for the project. Which process group are you in?

Options:

A.

Planning

B.

Monitoring and Controlling

C.

Executing

D.

Initiating

Discussion
Question 38

You are the project manager and are considering recommending a project that costs $280,000; expected inflows are $10,000 per quarter for the first two years and then $25,000 per quarter thereafter. What is the payback period?

Options:

A.

48 months

B.

40 months

C.

36 months

D.

50 months

Discussion
Question 39

If BCWP =400, ACWP = 410, and BCWS = 350, what is the cost performance index?

Options:

A.

0-413

B.

0-82

C.

1-06

D.

1-142

Discussion