Question 40

A project sponsor has requested documentation to determine the scheduled activities for a project that is

running behind schedule. Which of the following documents should the project manager send to the sponsor to

quickly identify the project activities?

Options:

A.

RACI

B.

SWOT

C.

SOW

D.

WBS

Discussion
Nell
Are these dumps reliable?
Ernie Jul 13, 2025
Yes, very much so. Cramkey Dumps are created by experienced and certified professionals who have gone through the exams themselves. They understand the importance of providing accurate and relevant information to help you succeed.
Billy
It was like deja vu! I was confident going into the exam because I had already seen those questions before.
Vincent Jul 20, 2025
Definitely. And the best part is, I passed! I feel like all that hard work and preparation paid off. Cramkey is the best resource for all students!!!
Addison
Want to tell everybody through this platform that I passed my exam with excellent score. All credit goes to Cramkey Exam Dumps.
Libby Jul 11, 2025
That's good to know. I might check it out for my next IT certification exam. Thanks for the info.
Mariam
Do anyone think Cramkey questions can help improve exam scores?
Katie Jul 6, 2025
Absolutely! Many people have reported improved scores after using Cramkey Dumps, and there are also success stories of people passing exams on the first try. I already passed this exam. I confirmed above questions were in exam.
Osian
Dumps are fantastic! I recently passed my certification exam using these dumps and I must say, they are 100% valid.
Azaan Jul 17, 2025
They are incredibly accurate and valid. I felt confident going into my exam because the dumps covered all the important topics and the questions were very similar to what I saw on the actual exam. The team of experts behind Cramkey Dumps make sure the information is relevant and up-to-date.
Question 41

When forming a project team, there are a number of phases.

When a project team is productive and effective this phase is known as which of the following?

Options:

A.

Forming

B.

Norming

C.

Performing

D.

Storming

Discussion
Question 42

Which of the following activities are associated with the closing phase of a project? (Choose two.)

Options:

A.

Risk mitigation

B.

Archiving of project documents

C.

Tracking of expenditures

D.

Lessons learned

E.

Quality assurance

Discussion
Question 43

During the execution phase of a project, a project task has run longer than anticipated.

Questions 43

Which of the following is the new critical path of the project if Task 2 requires an additional two days to complete?

Options:

A.

12 days

B.

14 days

C.

16 days

D.

19 days

Discussion