Question 104

When developing a project schedule, which of the following resources is the BEST to estimate task duration?

Options:

A.

Project manager

B.

Project scheduler

C.

Project team

D.

Project sponsor

Discussion
Aryan
Absolutely rocked! They are an excellent investment for anyone who wants to pass the exam on the first try. They save you time and effort by providing a comprehensive overview of the exam content, and they give you a competitive edge by giving you access to the latest information. So, I definitely recommend them to new students.
Jessie May 22, 2026
did you use PDF or Engine? Which one is most useful?
Miley
Hey, I tried Cramkey Dumps for my IT certification exam. They are really awesome and helped me pass my exam with wonderful score.
Megan May 25, 2026
That’s great!!! I’ll definitely give it a try. Thanks!!!
Teddie
yes, I passed my exam with wonderful score, Accurate and valid dumps.
Isla-Rose May 12, 2026
Absolutely! The questions in the dumps were almost identical to the ones that appeared in the actual exam. I was able to answer almost all of them correctly.
Ayesha
They are study materials that are designed to help students prepare for exams and certification tests. They are basically a collection of questions and answers that are likely to appear on the test.
Ayden May 7, 2026
That sounds interesting. Why are they useful? Planning this week, hopefully help me. Can you give me PDF if you have ?
Question 105

A project manager chose an architect based on the architect’s presentation, but company policy states vendors must be selected based on the lowest bid. Which of the following applies to this situation?

Options:

A.

The PMO did not sign a letter of intent.

B.

The project manager neglected to conduct a communication requirements analysis.

C.

The project sponsor was not consulted in the final decision-making process.

D.

The project manager did not conform to the compliance standard.

Discussion
Question 106

Joe, a team member, is dissatisfied with his assigned project tasks, and he communicates this to his manager. His manager arranges a meeting with the project manager. Together, they decide Joe needs additional training to be able to execute the assigned project tasks. Which of the following is the company's organizational structure?

Options:

A.

Projectized

B.

Vertical

C.

Matrix

D.

Functional

Discussion
Question 107

Some resources are waiting to be assigned to a new project. These resources are called:

Options:

A.

underqualified resources.

B.

benched resources.

C.

dedicated resources.

D.

overallocated resources.