Month End Sale Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: get65

CompTIA Updated PK0-004 Exam Questions and Answers by gideon

Page: 18 / 29

CompTIA PK0-004 Exam Overview :

Exam Name: CompTIA Project+ Exam
Exam Code: PK0-004 Dumps
Vendor: CompTIA Certification: Project+
Questions: 796 Q&A's Shared By: gideon
Question 72

After identifying all known tasks, the project manager has started to sequence and set durations.

Which of the following describes how the project manager should BEST determine the initial sequence and durations?

Options:

A.

Use milestones identified in the project charter.

B.

Use data based on past knowledge.

C.

Hold a full team workshop to review the complete WBS.

D.

Collaborate with other project managers.

Discussion
Addison
Want to tell everybody through this platform that I passed my exam with excellent score. All credit goes to Cramkey Exam Dumps.
Libby Jul 11, 2025
That's good to know. I might check it out for my next IT certification exam. Thanks for the info.
Marley
Hey, I heard the good news. I passed the certification exam!
Jaxson Jul 13, 2025
Yes, I passed too! And I have to say, I couldn't have done it without Cramkey Dumps.
Ivan
I tried these dumps for my recent certification exam and I found it pretty helpful.
Elis Jul 4, 2025
Agree!!! The questions in the dumps were quite similar to what came up in the actual exam. It gave me a good idea of the types of questions to expect and helped me revise efficiently.
Vienna
I highly recommend them. They are offering exact questions that we need to prepare our exam.
Jensen Jul 4, 2025
That's great. I think I'll give Cramkey a try next time I take a certification exam. Thanks for the recommendation!
Question 73

A project manager is creating the WBS.

In which of the following phases is the project?

Options:

A.

Initiation

B.

Planning

C.

Execution

D.

Closing

Discussion
Question 74

A project team has purchased computers with warranties extending throughout the entire project. Which of the following represents the risk strategy utilized?

Options:

A.

Transfer

B.

Share

C.

Mitigate

D.

Avoid

Discussion
Question 75

Team members have reported that meetings are poorly attended and unproductive.

Which of the following steps can the project manager take to make the meetings more productive?

Options:

A.

Discontinue the meetings with the poorest attendance.

B.

Decrease the length of the meetings.

C.

Distribute an agenda before each meeting.

D.

Document team member attendance and report it to management.

Discussion
Page: 18 / 29
Title
Questions
Posted

PK0-004
PDF

$36.75  $104.99

PK0-004 Testing Engine

$43.75  $124.99

PK0-004 PDF + Testing Engine

$57.75  $164.99