Question 72

After identifying all known tasks, the project manager has started to sequence and set durations.

Which of the following describes how the project manager should BEST determine the initial sequence and durations?

Options:

A.

Use milestones identified in the project charter.

B.

Use data based on past knowledge.

C.

Hold a full team workshop to review the complete WBS.

D.

Collaborate with other project managers.

Discussion
Alaia
These Dumps are amazing! I used them to study for my recent exam and I passed with flying colors. The information in the dumps is so valid and up-to-date. Thanks a lot!!!
Zofia Dec 3, 2025
That's great to hear! I've been struggling to find good study material for my exam. I will ty it for sure.
Nell
Are these dumps reliable?
Ernie Dec 16, 2025
Yes, very much so. Cramkey Dumps are created by experienced and certified professionals who have gone through the exams themselves. They understand the importance of providing accurate and relevant information to help you succeed.
Stefan
Thank you so much Cramkey I passed my exam today due to your highly up to date dumps.
Ocean Dec 13, 2025
Agree….Cramkey Dumps are constantly updated based on changes in the exams. They also have a team of experts who regularly review the materials to ensure their accuracy and relevance. This way, you can be sure you're studying the most up-to-date information available.
Anya
I must say they're considered the best dumps available and the questions are very similar to what you'll see in the actual exam. Recommended!!!
Cassius Dec 28, 2025
Yes, they offer a 100% success guarantee. And many students who have used them have reported passing their exams with flying colors.
Marley
Hey, I heard the good news. I passed the certification exam!
Jaxson Dec 5, 2025
Yes, I passed too! And I have to say, I couldn't have done it without Cramkey Dumps.
Question 73

A project manager is creating the WBS.

In which of the following phases is the project?

Options:

A.

Initiation

B.

Planning

C.

Execution

D.

Closing

Discussion
Question 74

A project team has purchased computers with warranties extending throughout the entire project. Which of the following represents the risk strategy utilized?

Options:

A.

Transfer

B.

Share

C.

Mitigate

D.

Avoid

Discussion
Question 75

Team members have reported that meetings are poorly attended and unproductive.

Which of the following steps can the project manager take to make the meetings more productive?

Options:

A.

Discontinue the meetings with the poorest attendance.

B.

Decrease the length of the meetings.

C.

Distribute an agenda before each meeting.

D.

Document team member attendance and report it to management.