Question 72

After identifying all known tasks, the project manager has started to sequence and set durations.

Which of the following describes how the project manager should BEST determine the initial sequence and durations?

Options:

A.

Use milestones identified in the project charter.

B.

Use data based on past knowledge.

C.

Hold a full team workshop to review the complete WBS.

D.

Collaborate with other project managers.

Discussion
Conor
I recently used these dumps for my exam and I must say, I was impressed with their authentic material.
Yunus Sep 11, 2025
Exactly…….The information in the dumps is so authentic and up-to-date. Plus, the questions are very similar to what you'll see on the actual exam. I felt confident going into the exam because I had studied using Cramkey Dumps.
Laila
They're such a great resource for anyone who wants to improve their exam results. I used these dumps and passed my exam!! Happy customer, always prefer. Yes, same questions as above I know you guys are perfect.
Keira Sep 3, 2025
100% right….And they're so affordable too. It's amazing how much value you get for the price.
Atlas
What are these Dumps? Would anybody please explain it to me.
Reign Sep 22, 2025
These are exam dumps for a variety of IT certifications. They have a vast collection of updated questions and answers, which are very helpful in preparing for the exams.
Faye
Yayyyy. I passed my exam. I think all students give these dumps a try.
Emmeline Sep 15, 2025
Definitely! I have no doubt new students will find them to be just as helpful as I did.
Question 73

A project manager is creating the WBS.

In which of the following phases is the project?

Options:

A.

Initiation

B.

Planning

C.

Execution

D.

Closing

Discussion
Question 74

A project team has purchased computers with warranties extending throughout the entire project. Which of the following represents the risk strategy utilized?

Options:

A.

Transfer

B.

Share

C.

Mitigate

D.

Avoid

Discussion
Question 75

Team members have reported that meetings are poorly attended and unproductive.

Which of the following steps can the project manager take to make the meetings more productive?

Options:

A.

Discontinue the meetings with the poorest attendance.

B.

Decrease the length of the meetings.

C.

Distribute an agenda before each meeting.

D.

Document team member attendance and report it to management.