Question 68

The project manager has noticed a vendor is not performing in accordance with the SLA.

Which of the following items should the project manager use to highlight the vendor’s areas of poor performance?

Options:

A.

Balanced score card

B.

WBS

C.

Post-project evaluation

D.

PERT

Discussion
Question 69

A company has hired a new project manager. The PMO has briefed the new project manager on the following expected responsibilities for projects:

  • Coordinate project schedule
  • Manage to the triple constraint
  • Provide performance feedback to team members’ managers

Which of the following types of organizational structures did the new project manager MOST likely join?

Options:

A.

Balanced matrix

B.

Strong matrix

C.

Functional

D.

Projectized

Discussion
Faye
Yayyyy. I passed my exam. I think all students give these dumps a try.
Emmeline Sep 15, 2025
Definitely! I have no doubt new students will find them to be just as helpful as I did.
Ilyas
Definitely. I felt much more confident and prepared because of the Cramkey Dumps. I was able to answer most of the questions with ease and I think that helped me to score well on the exam.
Saoirse Sep 3, 2025
That's amazing. I'm glad you found something that worked for you. Maybe I should try them out for my next exam.
Ace
No problem! I highly recommend Cramkey Dumps to anyone looking to pass their certification exams. They will help you feel confident and prepared on exam day. Good luck!
Harris Sep 15, 2025
That sounds amazing. I'll definitely check them out. Thanks for the recommendation!
Lennie
I passed my exam and achieved wonderful score, I highly recommend it.
Emelia Sep 14, 2025
I think I'll give Cramkey a try next time I take a certification exam. Thanks for the recommendation!
Question 70

Which of the following is a key aspect of the Agile project management methodology?

Options:

A.

Test-driven

B.

Daily standup meetings

C.

Short project durations

D.

Defined list of requirements

Discussion
Question 71

A project manager does not have enough time to complete several tasks on a critical path. The budget is a low concern. Which of the following should be used to complete the tasks on time?

Options:

A.

Fast-track the tasks.

B.

Utilize positive float.

C.

Crash the schedule.

D.

Remove the critical path