Month End Sale Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: get65

CompTIA Updated PK0-004 Exam Questions and Answers by bridget

Page: 5 / 29

CompTIA PK0-004 Exam Overview :

Exam Name: CompTIA Project+ Exam
Exam Code: PK0-004 Dumps
Vendor: CompTIA Certification: Project+
Questions: 796 Q&A's Shared By: bridget
Question 20

Which of the following statements are correct regarding project management? (Select two.)

Options:

A.

A project can be part of an organization’s program management.

B.

An organization’s portfolio will include programs.

C.

A program has a defined start and finish.

D.

An organization’s portfolio is a temporary and unique endeavor.

E.

A project portfolio will be managed under program management.

Discussion
Question 21

A sponsor requests that the project team shorten the completion of a project by two months to give the sales team more leverage in renegotiating the contract with the client. The budgeted time is 500 hours, and the projected earned value is $30,000.

Questions 21

Which of the following represents the cost variance for both project completions?

Options:

A.

-$4.8K and -$7K

B.

-$4.9K and $7K

C.

$4.8K and -$7K

D.

$4.8K and $7K

Discussion
Question 22

Which of the following analyses should a project manager use to determine problem areas for corrective action planning? (Select two.)

Options:

A.

Planned value

B.

Schedule variance

C.

Acceptable variance

D.

Cost variance

E.

Earned value

Discussion
Pippa
I was so happy to see that almost all the questions on the exam were exactly what I found in their Dumps.
Anastasia Sep 21, 2024
You are right…It was amazing! The Cramkey Dumps were so comprehensive and well-organized, it made studying for the exam a breeze.
Cody
I used Cramkey Dumps to prepare and a lot of the questions on the exam were exactly what I found in their study materials.
Eric Sep 13, 2024
Really? That's great to hear! I used Cramkey Dumps too and I had the same experience. The questions were almost identical.
Andrew
Are these dumps helpful?
Jeremiah Oct 27, 2024
Yes, Don’t worry!!! I'm confident you'll find them to be just as helpful as I did. Good luck with your exam!
Wyatt
Passed my exam… Thank you so much for your excellent Exam Dumps.
Arjun Sep 18, 2024
That sounds really useful. I'll definitely check it out.
Question 23

A new stakeholder has requested the status and progress reports for the project milestones. Which of the following documents should the project manager address FIRST?

Options:

A.

Project communication plan

B.

Project status report

C.

Project management plan

D.

Project backlog

Discussion
Page: 5 / 29
Title
Questions
Posted

PK0-004
PDF

$36.75  $104.99

PK0-004 Testing Engine

$43.75  $124.99

PK0-004 PDF + Testing Engine

$57.75  $164.99