Month End Sale Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: get65

CompTIA Updated PK0-004 Exam Questions and Answers by denis

Page: 23 / 29

CompTIA PK0-004 Exam Overview :

Exam Name: CompTIA Project+ Exam
Exam Code: PK0-004 Dumps
Vendor: CompTIA Certification: Project+
Questions: 796 Q&A's Shared By: denis
Question 92

A project manager holds weekly project status meetings with the project team and an outside contractor. One of the team members is best friends with the contractor, so discussions often go off-track and meetings last longer than planned. Which of the following is the BEST step for the project manager to take to resolve this issue?

Options:

A.

Establish what will be discussed before the meeting and ensure the agenda is followed.

B.

Talk to the team member about keeping personal discussions outside the meeting.

C.

Reinforce the established project communication plan.

D.

Take charge of the meeting by not allowing side-talking.

Discussion
Anya
I must say they're considered the best dumps available and the questions are very similar to what you'll see in the actual exam. Recommended!!!
Cassius Jul 6, 2025
Yes, they offer a 100% success guarantee. And many students who have used them have reported passing their exams with flying colors.
Freddy
I passed my exam with flying colors and I'm confident who will try it surely ace the exam.
Aleksander Jul 24, 2025
Thanks for the recommendation! I'll check it out.
Lennox
Something Special that they provide a comprehensive overview of the exam content. They cover all the important topics and concepts, so you can be confident that you are well-prepared for the test.
Aiza Jul 21, 2025
That makes sense. What makes Cramkey Dumps different from other study materials?
Marley
Hey, I heard the good news. I passed the certification exam!
Jaxson Jul 13, 2025
Yes, I passed too! And I have to say, I couldn't have done it without Cramkey Dumps.
Question 93

A senior developer abruptly resigned without notice. Because of the senior developer’s expertise, the active task workload was substantial.

This would MOST likely impact the project’s: (Choose two.)

Options:

A.

environment

B.

scheduling

C.

requirements

D.

effectiveness

E.

scope

F.

budget

Discussion
Question 94

A project team decides to obtain a support contact on one of the hardware infrastructures being used on the project. This is to ensure the project is grounded if an issue with the hardware occurs during the course of the project.

This type of risk response is known as:

Options:

A.

mitigation.

B.

avoidance.

C.

transference.

D.

acceptance.

Discussion
Question 95

Collaboration tools are BEST used instead of email when multiple people are:

Options:

A.

scheduling a meeting.

B.

communicating the agenda for a meeting.

C.

conducting research for a meeting.

D.

working on document for a meeting.

Discussion
Page: 23 / 29
Title
Questions
Posted

PK0-004
PDF

$36.75  $104.99

PK0-004 Testing Engine

$43.75  $124.99

PK0-004 PDF + Testing Engine

$57.75  $164.99