Question 8

A project team completed a brainstorming activity to determine potential issues with a project. Which of the following activities should the project team do NEXT?

Options:

A.

Risk identification

B.

Risk quantification

C.

Risk planning

D.

Risk response

Discussion
Question 9

During a CCB, a SME evaluated the impact and provided new information because of business process

changes for handling potential failure. Which of the following documents should be updated?

Options:

A.

Incident response

B.

Project plan

C.

Risk register

D.

Business continuity plan

Discussion
Reeva
Wow what a success I achieved today. Thank you so much Cramkey for amazing Dumps. All students must try it.
Amari Dec 18, 2025
Wow, that's impressive. I'll definitely keep Cramkey in mind for my next exam.
Nia
Why are these Dumps so important for students these days?
Mary Dec 19, 2025
With the constantly changing technology and advancements in the industry, it's important for students to have access to accurate and valid study material. Cramkey Dumps provide just that. They are constantly updated to reflect the latest changes and ensure that the information is up-to-date.
Peyton
Hey guys. Guess what? I passed my exam. Thanks a lot Cramkey, your provided information was relevant and reliable.
Coby Dec 1, 2025
Thanks for sharing your experience. I think I'll give Cramkey a try for my next exam.
Ari
Can anyone explain what are these exam dumps and how are they?
Ocean Dec 20, 2025
They're exam preparation materials that are designed to help you prepare for various certification exams. They provide you with up-to-date and accurate information to help you pass your exams.
Erik
Hey, I have passed my exam using Cramkey Dumps?
Freyja Dec 14, 2025
Really, what are they? All come in your pool? Please give me more details, I am going to have access their subscription. Please brother, give me more details.
Question 10

Ann, one of the affected stakeholders, feels that the project team has not been giving periodic stakeholder updates and that her input has not been taken into account.

Which of the following should the project manager do to ensure stakeholder expectations are met?

Options:

A.

Ensure that Ann is involved during the testing phase of the project so she can call out functional gaps.

B.

Organize a walkthrough of the solution and ensure face-to-face updates occur every two weeks.

C.

Escalate the issue to the project steering committee that Ann is criticizing the project quality.

D.

Organize a requirements workshop to capture any gaps.

Discussion
Question 11

Which of the following charts is a mathematical diagram used to values for two variables for a set of data?

Options:

A.

Histogram

B.

Fishbone

C.

Gantt

D.

Scatter