Question 84

Which of the following is a suitable situation in which to apply the Agile methodology?

Options:

A.

A very well-defined RFP

B.

A fixed price contract

C.

High-level requirements

D.

Clear goals and large teams

Discussion
Question 85

A project is nearing the expected completion date, but it is behind schedule. The project manager has decided to fast-track the resources.

Which of the following impacts will MOST likely occur? (Choose two.)

Options:

A.

Cost will increase.

B.

Scope will increase.

C.

Schedule will decrease.

D.

Risk will decrease.

E.

Budget will increase.

F.

Quality will increase.

Discussion
Zayaan
Successfully aced the exam… Thanks a lot for providing amazing Exam Dumps.
Harmony Sep 16, 2025
That's fantastic! I'm glad to hear that their dumps helped you. I also used them and found it accurate.
Conor
I recently used these dumps for my exam and I must say, I was impressed with their authentic material.
Yunus Sep 11, 2025
Exactly…….The information in the dumps is so authentic and up-to-date. Plus, the questions are very similar to what you'll see on the actual exam. I felt confident going into the exam because I had studied using Cramkey Dumps.
Norah
Cramkey is highly recommended.
Zayan Sep 15, 2025
Definitely. If you're looking for a reliable and effective study resource, look no further than Cramkey Dumps. They're simply wonderful!
Ari
Can anyone explain what are these exam dumps and how are they?
Ocean Sep 17, 2025
They're exam preparation materials that are designed to help you prepare for various certification exams. They provide you with up-to-date and accurate information to help you pass your exams.
Question 86

The project coordinator creates the following list to track the items team members are working on:

Questions 86

Which of the following types of documents is shown in the table above?

Options:

A.

Project schedule

B.

Project charter

C.

Action item log

D.

Work breakdown structure

Discussion
Question 87

During a meeting, the project manager abruptly interrupts the discussion of two team members who have not reached an agreement on a particular requirement and continues with the meeting.

Which of the following conflict resolutions is the project manager performing?

Options:

A.

Smoothing

B.

Forcing

C.

Confronting

D.

Avoiding

Discussion
Page: 21 / 29
Title
Questions
Posted

PK0-004
PDF

$36.75  $104.99

PK0-004 Testing Engine

$43.75  $124.99

PK0-004 PDF + Testing Engine

$57.75  $164.99