Question 88

An organization is divided into three separate entities based on geographical region. Which of the following

types of organizational change is this?

Options:

A.

Relocation

B.

Outsourcing

C.

Demerger

D.

Split

Discussion
Question 89

A project manager detects low performance from a team member who previously demonstrated to be a highly

skilled asset. The team member explains that being part of two teams is too time consuming. This is a disadvantage of having:

Options:

A.

dedicated resources.

B.

interproject dependencies.

C.

resource overallocation.

D.

shared resources.

Discussion
Question 90

A project manager launched a survey for future end users of a new product under development. The sponsor received the survey results and realized the needs are different than the features currently being developed. The sponsor decided to cancel the project. Which of the following explains why the sponsor made this decision?

Options:

A.

Constraint reprioritization needed to be carried out.

B.

The cost of the changes would be more than planned.

C.

The survey was not stated in the project management plan.

D.

More than half of the project charter should be updated.

Discussion
Question 91

A homeowner wants to build a fence. It will take:

A quarter of a day to measure the length of the fence

Half a day to acquire the materials

A quarter of a day to dig holes for the posts

A quarter of a day to set the posts with concrete

Two days for the concrete to dry

While the concrete is drying, the homeowner will spend a quarter of a day cutting the lateral pieces to size, half a day applying the coating to the remaining pieces, and then three days waiting for the coating to dry. It will then take the homeowner one day to assemble the fence. Which of the following is the length of time it will take the homeowner to build the fence?

Options:

A.

Six days

B.

Seven days

C.

Eight days

D.

Nine days

Discussion
Josephine
I want to ask about their study material and Customer support? Can anybody guide me?
Zayd Oct 22, 2024
Yes, the dumps or study material provided by them are authentic and up to date. They have a dedicated team to assist students and make sure they have a positive experience.
Sam
Can I get help from these dumps and their support team for preparing my exam?
Audrey Aug 29, 2024
Definitely, you won't regret it. They've helped so many people pass their exams and I'm sure they'll help you too. Good luck with your studies!
Hassan
Highly Recommended Dumps… today I passed my exam! Same questions appear. I bought Full Access.
Kasper Oct 20, 2024
Hey wonderful….so same questions , sounds good. Planning to write this week, I will go for full access today.
Nell
Are these dumps reliable?
Ernie Oct 10, 2024
Yes, very much so. Cramkey Dumps are created by experienced and certified professionals who have gone through the exams themselves. They understand the importance of providing accurate and relevant information to help you succeed.
Mariam
Do anyone think Cramkey questions can help improve exam scores?
Katie Nov 2, 2024
Absolutely! Many people have reported improved scores after using Cramkey Dumps, and there are also success stories of people passing exams on the first try. I already passed this exam. I confirmed above questions were in exam.
Page: 22 / 29
Title
Questions
Posted

PK0-004
PDF

$36.75  $104.99

PK0-004 Testing Engine

$43.75  $124.99

PK0-004 PDF + Testing Engine

$57.75  $164.99