Question 88

An organization is divided into three separate entities based on geographical region. Which of the following

types of organizational change is this?

Options:

A.

Relocation

B.

Outsourcing

C.

Demerger

D.

Split

Discussion
Wyatt
Passed my exam… Thank you so much for your excellent Exam Dumps.
Arjun May 15, 2026
That sounds really useful. I'll definitely check it out.
Freddy
I passed my exam with flying colors and I'm confident who will try it surely ace the exam.
Aleksander May 15, 2026
Thanks for the recommendation! I'll check it out.
Ernest
That's amazing. I think I'm going to give Cramkey Dumps a try for my next exam. Thanks for telling me about them! CramKey admin please share more questions……You guys are amazing.
Nate May 21, 2026
I failed last week, I never know this site , but amazed to see all these questions were in my exam week before. I feel bad now, why I didn’t bother this site. Thanks Cramkey, Excellent Job.
Cecilia
Yes, I passed my certification exam using Cramkey Dumps.
Helena May 28, 2026
Great. Yes they are really effective
Fatima
Hey I passed my exam. The world needs to know about it. I have never seen real exam questions on any other exam preparation resource like I saw on Cramkey Dumps.
Niamh May 4, 2026
That's true. Cramkey Dumps are simply the best when it comes to preparing for the certification exam. They have all the key information you need and the questions are very similar to what you'll see on the actual exam.
Question 89

A project manager detects low performance from a team member who previously demonstrated to be a highly

skilled asset. The team member explains that being part of two teams is too time consuming. This is a disadvantage of having:

Options:

A.

dedicated resources.

B.

interproject dependencies.

C.

resource overallocation.

D.

shared resources.

Discussion
Question 90

A project manager launched a survey for future end users of a new product under development. The sponsor received the survey results and realized the needs are different than the features currently being developed. The sponsor decided to cancel the project. Which of the following explains why the sponsor made this decision?

Options:

A.

Constraint reprioritization needed to be carried out.

B.

The cost of the changes would be more than planned.

C.

The survey was not stated in the project management plan.

D.

More than half of the project charter should be updated.

Discussion
Question 91

A homeowner wants to build a fence. It will take:

A quarter of a day to measure the length of the fence

Half a day to acquire the materials

A quarter of a day to dig holes for the posts

A quarter of a day to set the posts with concrete

Two days for the concrete to dry

While the concrete is drying, the homeowner will spend a quarter of a day cutting the lateral pieces to size, half a day applying the coating to the remaining pieces, and then three days waiting for the coating to dry. It will then take the homeowner one day to assemble the fence. Which of the following is the length of time it will take the homeowner to build the fence?

Options:

A.

Six days

B.

Seven days

C.

Eight days

D.

Nine days