Question 88

An organization is divided into three separate entities based on geographical region. Which of the following

types of organizational change is this?

Options:

A.

Relocation

B.

Outsourcing

C.

Demerger

D.

Split

Discussion
Norah
Cramkey is highly recommended.
Zayan Sep 15, 2025
Definitely. If you're looking for a reliable and effective study resource, look no further than Cramkey Dumps. They're simply wonderful!
Kingsley
Do anyone guide my how these dumps would be helpful for new students like me?
Haris Sep 25, 2025
Absolutely! They are highly recommended for anyone looking to pass their certification exam. The dumps are easy to understand and follow, making it easier for you to study and retain the information.
Laila
They're such a great resource for anyone who wants to improve their exam results. I used these dumps and passed my exam!! Happy customer, always prefer. Yes, same questions as above I know you guys are perfect.
Keira Sep 3, 2025
100% right….And they're so affordable too. It's amazing how much value you get for the price.
Fatima
Hey I passed my exam. The world needs to know about it. I have never seen real exam questions on any other exam preparation resource like I saw on Cramkey Dumps.
Niamh Sep 2, 2025
That's true. Cramkey Dumps are simply the best when it comes to preparing for the certification exam. They have all the key information you need and the questions are very similar to what you'll see on the actual exam.
Question 89

A project manager detects low performance from a team member who previously demonstrated to be a highly

skilled asset. The team member explains that being part of two teams is too time consuming. This is a disadvantage of having:

Options:

A.

dedicated resources.

B.

interproject dependencies.

C.

resource overallocation.

D.

shared resources.

Discussion
Question 90

A project manager launched a survey for future end users of a new product under development. The sponsor received the survey results and realized the needs are different than the features currently being developed. The sponsor decided to cancel the project. Which of the following explains why the sponsor made this decision?

Options:

A.

Constraint reprioritization needed to be carried out.

B.

The cost of the changes would be more than planned.

C.

The survey was not stated in the project management plan.

D.

More than half of the project charter should be updated.

Discussion
Question 91

A homeowner wants to build a fence. It will take:

A quarter of a day to measure the length of the fence

Half a day to acquire the materials

A quarter of a day to dig holes for the posts

A quarter of a day to set the posts with concrete

Two days for the concrete to dry

While the concrete is drying, the homeowner will spend a quarter of a day cutting the lateral pieces to size, half a day applying the coating to the remaining pieces, and then three days waiting for the coating to dry. It will then take the homeowner one day to assemble the fence. Which of the following is the length of time it will take the homeowner to build the fence?

Options:

A.

Six days

B.

Seven days

C.

Eight days

D.

Nine days