Question 56

The key stakeholders have reported the project pace as being slow. The project sponsor would like to cancel the project if it cannot be completed before the end of the year. The project is scheduled to be completed three months after the requested date.

To alter the pace of the project, which of the following should the project manager do FIRST?

Options:

A.

Give approval for the change requested by the project sponsor.

B.

Deny the request from the project sponsor.

C.

Document the change request from the project sponsor.

D.

Ask the project sponsor to change the request.

Discussion
Hendrix
Great website with Great Exam Dumps. Just passed my exam today.
Luka Mar 13, 2026
Absolutely. Cramkey Dumps only provides the latest and most updated exam questions and answers.
Miley
Hey, I tried Cramkey Dumps for my IT certification exam. They are really awesome and helped me pass my exam with wonderful score.
Megan Mar 4, 2026
That’s great!!! I’ll definitely give it a try. Thanks!!!
Freddy
I passed my exam with flying colors and I'm confident who will try it surely ace the exam.
Aleksander Mar 13, 2026
Thanks for the recommendation! I'll check it out.
Marley
Hey, I heard the good news. I passed the certification exam!
Jaxson Mar 25, 2026
Yes, I passed too! And I have to say, I couldn't have done it without Cramkey Dumps.
Syeda
I passed, Thank you Cramkey for your precious Dumps.
Stella Mar 17, 2026
That's great. I think I'll give Cramkey Dumps a try.
Question 57

The business stakeholder has been engaged late and has just had a chance to review the approved requirements. Consequently, it has been identified that there are a number of gaps in the requirements which are critical to the stakeholders's business unit.

Which of the following actions should the project manager take?

Options:

A.

Initiate change control.

B.

Follow communications plan.

C.

Manage project quality.

D.

Prepare a performance report.

Discussion
Question 58

A project manager has received a change order that will reduce a project's timeline and budget. However, the change order also indicates the goals and deliverables of the project must remain unchanged. Which of the following is the MOST logical impact to the project?

Options:

A.

The reduced timeline will impact the quality of the deliverables because the amount of time to test will be reduced.

B.

The reduced budget will result in reduced resources, which will lead to a strong matrix organizational structure being used.

C.

The reduced timeline will decrease risk, resulting in an increased contingency reserve.

D.

The reduced budget will cause the project manager to reject the change order.

Discussion
Question 59

A project manager would like to bring vendors into a new project. Which of the following documents should the potential vendors submit so the project manager can find the best vendors for the project?

Options:

A.

SLA

B.

SOW

C.

Change request

D.

RFP

Discussion