Week End Sale Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: get65

PMI Updated CA0-001 Exam Questions and Answers by jameson

Page: 7 / 19

PMI CA0-001 Exam Overview :

Exam Name: Certified Associate in Project Management (CAPM) Certification
Exam Code: CA0-001 Dumps
Vendor: PMI Certification: CAPM
Questions: 525 Q&A's Shared By: jameson
Question 28

Which statement is true about Bottom-up estimating?

Options:

A.

Estimating the cost of individual work items and then rolling up the costs to arrive at a project total.

B.

Uses the actual cost of a previous similar project as the basis for estimating the cost of the current project.

C.

Using project characteristics (or parameters) in a mathematical model to predict costs.

D.

Cost of quality can also be used to prepare the schedule activity cost estimate.

Discussion
Mylo
Excellent dumps with authentic information… I passed my exam with brilliant score.
Dominik Jan 1, 2026
That's amazing! I've been looking for good study material that will help me prepare for my upcoming certification exam. Now, I will try it.
Alessia
Amazing Dumps. Found almost all questions in actual exam whih I prepared from these valuable dumps. Recommended!!!!
Belle Jan 4, 2026
That's impressive. I've been struggling with finding good study material for my certification. Maybe I should give Cramkey Dumps a try.
Yusra
I passed my exam. Cramkey Dumps provides detailed explanations for each question and answer, so you can understand the concepts better.
Alisha Jan 26, 2026
I recently used their dumps for the certification exam I took and I have to say, I was really impressed.
Carson
Yeah, definitely. I would definitely recommend Cramkey Dumps to anyone who is preparing for an exam.
Rufus Jan 26, 2026
Me too. They're a lifesaver!
Rosalie
I passed. I would like to tell all students that they should definitely give Cramkey Dumps a try.
Maja Jan 23, 2026
That sounds great. I'll definitely check them out. Thanks for the suggestion!
Question 29

Who is responsible for the creation of the final project plan?

Options:

A.

Project Manager

B.

Team Leader

C.

Sponsor

D.

Project Team

Discussion
Question 30

Which time estimating tools estimate the basis for activity durations can be quantitatively determined by multiplying the quantity of work to be performed by the productivity rate?

Options:

A.

Parametric estimating

B.

Funding limit reconciliation

C.

Reserves analysis

D.

None of the above

Discussion
Question 31

Create Procurement document is done in _______.

Options:

A.

Plan Procurements

B.

Conduct Procurements

C.

Administer Procurements

D.

Close Procurements

Discussion
Page: 7 / 19

CA0-001
PDF

$36.75  $104.99

CA0-001 Testing Engine

$43.75  $124.99

CA0-001 PDF + Testing Engine

$57.75  $164.99