Question 36

If a project with a SPI of 0.8, what you tell?

Options:

A.

The project is running ahead of the schedule

B.

The project is running behind of the schedule

C.

Resources assigned to the project cost 1.8 units

D.

None

Discussion
Addison
Want to tell everybody through this platform that I passed my exam with excellent score. All credit goes to Cramkey Exam Dumps.
Libby Oct 3, 2025
That's good to know. I might check it out for my next IT certification exam. Thanks for the info.
Wyatt
Passed my exam… Thank you so much for your excellent Exam Dumps.
Arjun Oct 19, 2025
That sounds really useful. I'll definitely check it out.
Ernest
That's amazing. I think I'm going to give Cramkey Dumps a try for my next exam. Thanks for telling me about them! CramKey admin please share more questions……You guys are amazing.
Nate Oct 6, 2025
I failed last week, I never know this site , but amazed to see all these questions were in my exam week before. I feel bad now, why I didn’t bother this site. Thanks Cramkey, Excellent Job.
Ilyas
Definitely. I felt much more confident and prepared because of the Cramkey Dumps. I was able to answer most of the questions with ease and I think that helped me to score well on the exam.
Saoirse Oct 21, 2025
That's amazing. I'm glad you found something that worked for you. Maybe I should try them out for my next exam.
Nell
Are these dumps reliable?
Ernie Oct 21, 2025
Yes, very much so. Cramkey Dumps are created by experienced and certified professionals who have gone through the exams themselves. They understand the importance of providing accurate and relevant information to help you succeed.
Question 37

The end of the project comes after which of the following?

Options:

A.

Project charter

B.

Final deliverable

C.

Schedule

D.

QA activities are done

Discussion
Question 38

_________ is always the lowest risk for the buyer if the scope of work is not well defined.

Options:

A.

Cost plus incentive fee

B.

F'xed P|ice

C.

Time and material

D.

"'s^ 's nc* 'elated to price

Discussion
Question 39

Who has the responsibility for Plan Quality?

Options:

A.

Project manager

B.

QA manager

C.

Project planner

D.

Team lead

Discussion