Question 36

If a project with a SPI of 0.8, what you tell?

Options:

A.

The project is running ahead of the schedule

B.

The project is running behind of the schedule

C.

Resources assigned to the project cost 1.8 units

D.

None

Discussion
Peyton
Hey guys. Guess what? I passed my exam. Thanks a lot Cramkey, your provided information was relevant and reliable.
Coby (not set)
Thanks for sharing your experience. I think I'll give Cramkey a try for my next exam.
Lennox
Something Special that they provide a comprehensive overview of the exam content. They cover all the important topics and concepts, so you can be confident that you are well-prepared for the test.
Aiza (not set)
That makes sense. What makes Cramkey Dumps different from other study materials?
Mylo
Excellent dumps with authentic information… I passed my exam with brilliant score.
Dominik (not set)
That's amazing! I've been looking for good study material that will help me prepare for my upcoming certification exam. Now, I will try it.
Aryan
Absolutely rocked! They are an excellent investment for anyone who wants to pass the exam on the first try. They save you time and effort by providing a comprehensive overview of the exam content, and they give you a competitive edge by giving you access to the latest information. So, I definitely recommend them to new students.
Jessie (not set)
did you use PDF or Engine? Which one is most useful?
River
Hey, I used Cramkey Dumps to prepare for my recent exam and I passed it.
Lewis (not set)
Yeah, I used these dumps too. And I have to say, I was really impressed with the results.
Question 37

The end of the project comes after which of the following?

Options:

A.

Project charter

B.

Final deliverable

C.

Schedule

D.

QA activities are done

Discussion
Question 38

_________ is always the lowest risk for the buyer if the scope of work is not well defined.

Options:

A.

Cost plus incentive fee

B.

F'xed P|ice

C.

Time and material

D.

"'s^ 's nc* 'elated to price

Discussion
Question 39

Who has the responsibility for Plan Quality?

Options:

A.

Project manager

B.

QA manager

C.

Project planner

D.

Team lead

Discussion