PMI Updated CA0-001 Exam Questions and Answers by kaiden

Page: 3 / 19

PMI CA0-001 Exam Overview :

Exam Name: Certified Associate in Project Management (CAPM) Certification
Exam Code: CA0-001 Dumps
Vendor: PMI Certification: CAPM
Questions: 525 Q&A's Shared By: kaiden
Question 12

Which of the following is not part of project scope management?

Options:

A.

Verify Scope

B.

Collect Requirements

C.

Create WBS

D.

None of the above

Discussion
Nylah
I've been looking for good study material for my upcoming certification exam. Need help.
Dolly Oct 2, 2025
Then you should definitely give Cramkey Dumps a try. They have a huge database of questions and answers, making it easy to study and prepare for the exam. And the best part is, you can be sure the information is accurate and relevant.
Teddie
yes, I passed my exam with wonderful score, Accurate and valid dumps.
Isla-Rose Oct 23, 2025
Absolutely! The questions in the dumps were almost identical to the ones that appeared in the actual exam. I was able to answer almost all of them correctly.
Lois
I passed my exam with wonderful score. Their dumps are 100% valid and I felt confident during the exam.
Ernie Oct 10, 2025
Absolutely. The best part is, the answers in the dumps were correct. So, I felt confident and well-prepared for the exam.
Inaya
Passed the exam. questions are valid. The customer support is top-notch. They were quick to respond to any questions I had and provided me with all the information I needed.
Cillian Oct 9, 2025
That's a big plus. I've used other dump providers in the past and the customer support was often lacking.
Erik
Hey, I have passed my exam using Cramkey Dumps?
Freyja Oct 8, 2025
Really, what are they? All come in your pool? Please give me more details, I am going to have access their subscription. Please brother, give me more details.
Question 13

In PMBOK, the buyer is ________ to the project team.

Options:

A.

Internal

B.

External

C.

Outside

D.

Assigned

Discussion
Question 14

Which process must occur after a project manager has been assigned to the project?

Options:

A.

Collect Requirements

B.

Develop the project charter

C.

Develop the project statement of work

D.

Develop project closing document

Discussion
Question 15

Which of the following relationship is used in the Arrow Diagramming Method [ADM] :

Options:

A.

Start-to-Finish

B.

Finish-to-Start

C.

Start-to-Start

D.

Finish-to-Finish

Discussion