PMI Updated CA0-001 Exam Questions and Answers by adnan

Page: 10 / 19

PMI CA0-001 Exam Overview :

Exam Name: Certified Associate in Project Management (CAPM) Certification
Exam Code: CA0-001 Dumps
Vendor: PMI Certification: CAPM
Questions: 525 Q&A's Shared By: adnan
Question 40

A Risk Register is a part of the ________.

Options:

A.

Project Scope Statement

B.

Project Management plan

C.

Project Scheduling plan

D.

Project Charter

Discussion
Georgina
I used Cramkey Dumps to prepare for my recent exam and I have to say, they were a huge help.
Corey Apr 15, 2026
Really? How did they help you? I know these are the same questions appears in exam. I will give my try. But tell me if they also help in some training?
Carson
Yeah, definitely. I would definitely recommend Cramkey Dumps to anyone who is preparing for an exam.
Rufus Mar 31, 2026
Me too. They're a lifesaver!
Ari
Can anyone explain what are these exam dumps and how are they?
Ocean Apr 6, 2026
They're exam preparation materials that are designed to help you prepare for various certification exams. They provide you with up-to-date and accurate information to help you pass your exams.
Anya
I must say they're considered the best dumps available and the questions are very similar to what you'll see in the actual exam. Recommended!!!
Cassius Apr 19, 2026
Yes, they offer a 100% success guarantee. And many students who have used them have reported passing their exams with flying colors.
Question 41

__________ is providing detailed plans for tasks that are about to start in the near future using the most current information and revisiting future activities when they near their starting dates.

Options:

A.

Rolling wave planning

B.

Progressive elaboration

C.

Milestone detail planning

D.

Expert judgment

Discussion
Question 42

How many communication channels will be required in a project in which 5 individual are participating?

Options:

A.

10

B.

12

C.

4

D.

5

Discussion
Question 43

You are the project manager of a project. If there are approved changes to the original scope, what you do with the old original scope?

Options:

A.

Save the old versions

B.

No need to save old version

C.

Scrap the old version

D.

Old version is not required

Discussion