Question 44

Which of the following subsidiary plan contains the quality objectives for the project?

Options:

A.

Quality baseline

B.

Quality management plan

C.

Process improvement plan

D.

QA checklist

Discussion
Georgina
I used Cramkey Dumps to prepare for my recent exam and I have to say, they were a huge help.
Corey Nov 26, 2025
Really? How did they help you? I know these are the same questions appears in exam. I will give my try. But tell me if they also help in some training?
Victoria
Hey, guess what? I passed the certification exam! I couldn't have done it without Cramkey Dumps.
Isabel Nov 25, 2025
Same here! I was so surprised when I saw that almost all the questions on the exam were exactly what I found in their study materials.
Alaia
These Dumps are amazing! I used them to study for my recent exam and I passed with flying colors. The information in the dumps is so valid and up-to-date. Thanks a lot!!!
Zofia Nov 12, 2025
That's great to hear! I've been struggling to find good study material for my exam. I will ty it for sure.
Inaaya
Are these Dumps worth buying?
Fraser Nov 16, 2025
Yes, of course, they are necessary to pass the exam. They give you an insight into the types of questions that could come up and help you prepare effectively.
Question 45

Acceptance of the product should be ________.

Options:

A.

Formal

B.

Consistent

C.

Personal

D.

Verbal

Discussion
Question 46

Which of the following is the most important task of the project manager during the Execution and Control phase?

Options:

A.

Information management

B.

Maintain scope statement

C.

Maintain Charter

D.

Maintain Closing document

Discussion
Question 47

Which of the following statement is true about project charter?

Options:

A.

Provides a high level definition of the effort and its stakeholders

B.

Announces who is the project engineer

C.

Tells the newspapers and media when the project will end

D.

Announces who is the project sponsor

Discussion