Question 76

In the three-point estimating technique, if the most likely estimate for an activity to complete is 100 days, the optimistic estimate is 60 days, and the pessimistic estimate is 200 days, what is the expected duration in which the activity will be completed?

Options:

A.

90 days

B.

100 days

C.

110 days

D.

660 days

Discussion
Ella-Rose
Amazing website with excellent Dumps. I passed my exam and secured excellent marks!!!
Alisha Aug 19, 2026
Extremely accurate. They constantly update their materials with the latest exam questions and answers, so you can be confident that what you're studying is up-to-date.
Addison
Want to tell everybody through this platform that I passed my exam with excellent score. All credit goes to Cramkey Exam Dumps.
Libby Aug 1, 2026
That's good to know. I might check it out for my next IT certification exam. Thanks for the info.
Conor
I recently used these dumps for my exam and I must say, I was impressed with their authentic material.
Yunus Aug 20, 2026
Exactly…….The information in the dumps is so authentic and up-to-date. Plus, the questions are very similar to what you'll see on the actual exam. I felt confident going into the exam because I had studied using Cramkey Dumps.
Lennie
I passed my exam and achieved wonderful score, I highly recommend it.
Emelia Aug 13, 2026
I think I'll give Cramkey a try next time I take a certification exam. Thanks for the recommendation!
Walter
Yayyy!!! I passed my exam with the help of Cramkey Dumps. Highly appreciated!!!!
Angus Aug 5, 2026
YES….. I saw the same questions in the exam.
Question 77

The decomposition technique is used to do which of the following?

Options:

A.

Subdivide the estimated costs of individual activities

B.

Subdivide project deliverables and project work into smaller, more manageable components

C.

Relate the work packages to the performing organizational units

D.

Shorten the project schedule duration and the amount of resources needed

Discussion
Question 78

Rolling wave planning is used as a tool and a technique in which of the following processes?

Options:

A.

Estimate Activity Durations

B.

Define Activities

C.

Develop Schedule

D.

Sequence Activities