PMI CA0-001 Exam Overview :

Exam Name: Certified Associate in Project Management (CAPM) Certification
Exam Code: CA0-001 Dumps
Vendor: PMI Certification: CAPM
Questions: 525 Q&A's Shared By: amyra
Question 76

In the three-point estimating technique, if the most likely estimate for an activity to complete is 100 days, the optimistic estimate is 60 days, and the pessimistic estimate is 200 days, what is the expected duration in which the activity will be completed?

Options:

A.

90 days

B.

100 days

C.

110 days

D.

660 days

Discussion
Faye
Yayyyy. I passed my exam. I think all students give these dumps a try.
Emmeline Oct 7, 2026
Definitely! I have no doubt new students will find them to be just as helpful as I did.
Mylo
Excellent dumps with authentic information… I passed my exam with brilliant score.
Dominik Oct 12, 2026
That's amazing! I've been looking for good study material that will help me prepare for my upcoming certification exam. Now, I will try it.
Miley
Hey, I tried Cramkey Dumps for my IT certification exam. They are really awesome and helped me pass my exam with wonderful score.
Megan Oct 14, 2026
That’s great!!! I’ll definitely give it a try. Thanks!!!
Reeva
Wow what a success I achieved today. Thank you so much Cramkey for amazing Dumps. All students must try it.
Amari Oct 27, 2026
Wow, that's impressive. I'll definitely keep Cramkey in mind for my next exam.
Mariam
Do anyone think Cramkey questions can help improve exam scores?
Katie Oct 8, 2026
Absolutely! Many people have reported improved scores after using Cramkey Dumps, and there are also success stories of people passing exams on the first try. I already passed this exam. I confirmed above questions were in exam.
Question 77

The decomposition technique is used to do which of the following?

Options:

A.

Subdivide the estimated costs of individual activities

B.

Subdivide project deliverables and project work into smaller, more manageable components

C.

Relate the work packages to the performing organizational units

D.

Shorten the project schedule duration and the amount of resources needed

Discussion
Question 78

Rolling wave planning is used as a tool and a technique in which of the following processes?

Options:

A.

Estimate Activity Durations

B.

Define Activities

C.

Develop Schedule

D.

Sequence Activities

Discussion