11.11 Special Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: get65

PMI Updated CA0-001 Exam Questions and Answers by amyra

Page: 19 / 19

PMI CA0-001 Exam Overview :

Exam Name: Certified Associate in Project Management (CAPM) Certification
Exam Code: CA0-001 Dumps
Vendor: PMI Certification: CAPM
Questions: 525 Q&A's Shared By: amyra
Question 76

In the three-point estimating technique, if the most likely estimate for an activity to complete is 100 days, the optimistic estimate is 60 days, and the pessimistic estimate is 200 days, what is the expected duration in which the activity will be completed?

Options:

A.

90 days

B.

100 days

C.

110 days

D.

660 days

Discussion
Question 77

The decomposition technique is used to do which of the following?

Options:

A.

Subdivide the estimated costs of individual activities

B.

Subdivide project deliverables and project work into smaller, more manageable components

C.

Relate the work packages to the performing organizational units

D.

Shorten the project schedule duration and the amount of resources needed

Discussion
Question 78

Rolling wave planning is used as a tool and a technique in which of the following processes?

Options:

A.

Estimate Activity Durations

B.

Define Activities

C.

Develop Schedule

D.

Sequence Activities

Discussion
Page: 19 / 19

CA0-001
PDF

$35  $99.99

CA0-001 Testing Engine

$42  $119.99

CA0-001 PDF + Testing Engine

$56  $159.99