Question 76

In the three-point estimating technique, if the most likely estimate for an activity to complete is 100 days, the optimistic estimate is 60 days, and the pessimistic estimate is 200 days, what is the expected duration in which the activity will be completed?

Options:

A.

90 days

B.

100 days

C.

110 days

D.

660 days

Discussion
Zayaan
Successfully aced the exam… Thanks a lot for providing amazing Exam Dumps.
Harmony Sep 16, 2026
That's fantastic! I'm glad to hear that their dumps helped you. I also used them and found it accurate.
Norah
Cramkey is highly recommended.
Zayan Sep 16, 2026
Definitely. If you're looking for a reliable and effective study resource, look no further than Cramkey Dumps. They're simply wonderful!
Kylo
What makes Cramkey Dumps so reliable? Please guide.
Sami Sep 10, 2026
Well, for starters, they have a team of experts who are constantly updating their material to reflect the latest changes in the industry. Plus, they have a huge database of questions and answers, which makes it easy to study and prepare for the exam.
Amy
I passed my exam and found your dumps 100% relevant to the actual exam.
Lacey Sep 5, 2026
Yeah, definitely. I experienced the same.
Faye
Yayyyy. I passed my exam. I think all students give these dumps a try.
Emmeline Sep 26, 2026
Definitely! I have no doubt new students will find them to be just as helpful as I did.
Question 77

The decomposition technique is used to do which of the following?

Options:

A.

Subdivide the estimated costs of individual activities

B.

Subdivide project deliverables and project work into smaller, more manageable components

C.

Relate the work packages to the performing organizational units

D.

Shorten the project schedule duration and the amount of resources needed

Discussion
Question 78

Rolling wave planning is used as a tool and a technique in which of the following processes?

Options:

A.

Estimate Activity Durations

B.

Define Activities

C.

Develop Schedule

D.

Sequence Activities

Discussion