Question 20

You are the project manager of a project .You have just completed the Collect Requirements and Define Scope. What should you do next?

Options:

A.

Create WBS

B.

Vei*

C.

Value analysis

D.

Control Scope

Discussion
Mariam
Do anyone think Cramkey questions can help improve exam scores?
Katie Nov 2, 2024
Absolutely! Many people have reported improved scores after using Cramkey Dumps, and there are also success stories of people passing exams on the first try. I already passed this exam. I confirmed above questions were in exam.
Amy
I passed my exam and found your dumps 100% relevant to the actual exam.
Lacey Aug 9, 2024
Yeah, definitely. I experienced the same.
Alaia
These Dumps are amazing! I used them to study for my recent exam and I passed with flying colors. The information in the dumps is so valid and up-to-date. Thanks a lot!!!
Zofia Sep 9, 2024
That's great to hear! I've been struggling to find good study material for my exam. I will ty it for sure.
Peyton
Hey guys. Guess what? I passed my exam. Thanks a lot Cramkey, your provided information was relevant and reliable.
Coby Sep 6, 2024
Thanks for sharing your experience. I think I'll give Cramkey a try for my next exam.
Ace
No problem! I highly recommend Cramkey Dumps to anyone looking to pass their certification exams. They will help you feel confident and prepared on exam day. Good luck!
Harris Oct 31, 2024
That sounds amazing. I'll definitely check them out. Thanks for the recommendation!
Question 21

Which process group is for detailed resource assignments and responsibilities?

Options:

A.

Human resources management plan

B.

Project charter

C.

Aplan

D.

Project management plan

Discussion
Question 22

Which of the following is NOT input of Identify Risks?

Options:

A.

Project Charter

B.

Stakeholder Register

C.

Pis'* Management Plan

D.

Activity Cost Estimates

Discussion
Question 23

Which is not the tools and techniques used in Contract Administration:

Options:

A.

Contract change control system

B.

Contract negotiation

C.

Payment system

D.

Performance rating

Discussion