Question 72

Emphasizing areas of agreement rather than areas of difference is part which of the following conflict management techniques?

Options:

A.

Smoothing

B.

Compromising

C.

Avoiding

D.

Forcing

Discussion
Question 73

Many organizations categorize requirements into which of the following two categories?

Options:

A.

Project and Product

B.

Staffing and Budget

C.

Stakeholder and Customer

D.

Business and Technical

Discussion
Vienna
I highly recommend them. They are offering exact questions that we need to prepare our exam.
Jensen Jan 17, 2026
That's great. I think I'll give Cramkey a try next time I take a certification exam. Thanks for the recommendation!
Ivan
I tried these dumps for my recent certification exam and I found it pretty helpful.
Elis Jan 12, 2026
Agree!!! The questions in the dumps were quite similar to what came up in the actual exam. It gave me a good idea of the types of questions to expect and helped me revise efficiently.
Rosalie
I passed. I would like to tell all students that they should definitely give Cramkey Dumps a try.
Maja Jan 23, 2026
That sounds great. I'll definitely check them out. Thanks for the suggestion!
Anya
I must say they're considered the best dumps available and the questions are very similar to what you'll see in the actual exam. Recommended!!!
Cassius Jan 3, 2026
Yes, they offer a 100% success guarantee. And many students who have used them have reported passing their exams with flying colors.
Marley
Hey, I heard the good news. I passed the certification exam!
Jaxson Jan 25, 2026
Yes, I passed too! And I have to say, I couldn't have done it without Cramkey Dumps.
Question 74

Which of the following documents allows the project manager to assess risks that may require near term action?

Options:

A.

Probability and impact matrix

B.

Contingency analysis report

C.

Risk urgency assessment

D.

Rolling wave plan

Discussion
Question 75

What is the function of a Project Management Office (PMO)?

Options:

A.

To focus on the coordinated planning, prioritization, and execution of projects and subprojects that are tied to the parent organizations' or the client's overall business objectives.

B.

To coordinate and manage the procurement of projects relevant to the parent organization's business objectives and to administer the project charters accordingly.

C.

To administer performance reviews for the project manager and the project team members and to handle any personnel and payroll issues.

D.

To focus on the specified project objectives and to manage the scope, schedule, cost, and quality of the work packages.