PMI Updated CA0-001 Exam Questions and Answers by lockie

Page: 17 / 19

PMI CA0-001 Exam Overview :

Exam Name: Certified Associate in Project Management (CAPM) Certification
Exam Code: CA0-001 Dumps
Vendor: PMI Certification: CAPM
Questions: 525 Q&A's Shared By: lockie
Question 68

When is a project finished?

Options:

A.

After verbal acceptance of the customer or sponsor

B.

After lessons learned have been documented in contract closure

C.

When the project objectives have been met

D.

After resources have been released

Discussion
Lennox
Something Special that they provide a comprehensive overview of the exam content. They cover all the important topics and concepts, so you can be confident that you are well-prepared for the test.
Aiza Jul 21, 2025
That makes sense. What makes Cramkey Dumps different from other study materials?
Peyton
Hey guys. Guess what? I passed my exam. Thanks a lot Cramkey, your provided information was relevant and reliable.
Coby Jul 13, 2025
Thanks for sharing your experience. I think I'll give Cramkey a try for my next exam.
Fatima
Hey I passed my exam. The world needs to know about it. I have never seen real exam questions on any other exam preparation resource like I saw on Cramkey Dumps.
Niamh Jul 24, 2025
That's true. Cramkey Dumps are simply the best when it comes to preparing for the certification exam. They have all the key information you need and the questions are very similar to what you'll see on the actual exam.
Marley
Hey, I heard the good news. I passed the certification exam!
Jaxson Jul 13, 2025
Yes, I passed too! And I have to say, I couldn't have done it without Cramkey Dumps.
Honey
I highly recommend it. They made a big difference for me and I'm sure they'll help you too. Just make sure to use them wisely and not solely rely on them. They should be used as a supplement to your regular studies.
Antoni Jul 26, 2025
Good point. Thanks for the advice. I'll definitely keep that in mind.
Question 69

Which of the following is a tool or technique of the Collect Requirements process?

Options:

A.

Group decision making techniques

B.

Project management information system

C.

Alternative identification

D.

Communication requirement analysis

Discussion
Question 70

In an organization with a projectized organizational structure, who controls the project budget?

Options:

A.

Functional manager

B.

Project manager

C.

Program manager

D.

Project management office

Discussion
Question 71

Which of the following is an output of Define Scope?

Options:

A.

Project document updates

B.

Project management plan

C.

Scope baseline

D.

Product analysis

Discussion