Question 92

A project is about to start; however, the client is uncertain about the desired details for the final product. Which of the following methodologies should the project manager use?

Options:

A.

Agile

B.

SDLC

C.

Waterfall

D.

PRINCE2

Discussion
Question 93

A PM is working on a strategy to store records. Which of the following dements must be included in this plan? (Select TWO)

Options:

A.

Data management

B.

Issue management

C.

Work breakdown structure

D.

Document management

E.

Communication management

F.

Risk management

Discussion
Everleigh
I must say that they are updated regularly to reflect the latest exam content, so you can be sure that you are getting the most accurate information. Plus, they are easy to use and understand, so even new students can benefit from them.
Huxley Aug 19, 2025
That's great to know. So, you think new students should buy these dumps?
Ari
Can anyone explain what are these exam dumps and how are they?
Ocean Aug 20, 2025
They're exam preparation materials that are designed to help you prepare for various certification exams. They provide you with up-to-date and accurate information to help you pass your exams.
Fatima
Hey I passed my exam. The world needs to know about it. I have never seen real exam questions on any other exam preparation resource like I saw on Cramkey Dumps.
Niamh Aug 6, 2025
That's true. Cramkey Dumps are simply the best when it comes to preparing for the certification exam. They have all the key information you need and the questions are very similar to what you'll see on the actual exam.
Peyton
Hey guys. Guess what? I passed my exam. Thanks a lot Cramkey, your provided information was relevant and reliable.
Coby Aug 2, 2025
Thanks for sharing your experience. I think I'll give Cramkey a try for my next exam.
Question 94

Following a successful release, a project manager sent a survey to all stakeholders to gain an understanding of opportunity areas for the team. Which of the following can use the survey results as an input?

Options:

A.

Daily stand-up

B.

Project momentum

C.

Performance feedback

D.

Meeting minutes

Discussion
Question 95

Which of the following requires the MOST availability from the business team?

Options:

A.

SDLC

B.

Scrum

C.

PRINCE2

D.

Waterfall

Discussion