Question 16

Which of the following contract types in project procurement has the highest risk for the buyer?

Options:

A.

Time and material

B.

Cost-plus

C.

Fixed-price

D.

Unit price

Discussion
Honey
I highly recommend it. They made a big difference for me and I'm sure they'll help you too. Just make sure to use them wisely and not solely rely on them. They should be used as a supplement to your regular studies.
Antoni Aug 4, 2025
Good point. Thanks for the advice. I'll definitely keep that in mind.
Alaia
These Dumps are amazing! I used them to study for my recent exam and I passed with flying colors. The information in the dumps is so valid and up-to-date. Thanks a lot!!!
Zofia Aug 20, 2025
That's great to hear! I've been struggling to find good study material for my exam. I will ty it for sure.
Rae
I tried using Cramkey dumps for my recent certification exam and I found them to be more accurate and up-to-date compared to other dumps I've seen. Passed the exam with wonderful score.
Rayyan Aug 3, 2025
I see your point. Thanks for sharing your thoughts. I might give it a try for my next certification exam.
Amy
I passed my exam and found your dumps 100% relevant to the actual exam.
Lacey Aug 17, 2025
Yeah, definitely. I experienced the same.
Everleigh
I must say that they are updated regularly to reflect the latest exam content, so you can be sure that you are getting the most accurate information. Plus, they are easy to use and understand, so even new students can benefit from them.
Huxley Aug 19, 2025
That's great to know. So, you think new students should buy these dumps?
Question 17

Which of the following artifacts should project team members use if they want to identify who to communicate with and at what level?

Options:

A.

Concept of operations

B.

WBS

C.

Integrated master schedule

D.

RACI

Discussion
Question 18

How does data discovery assist with data classification'?

Options:

A.

It shows where specific data is stored

B.

It automatically classifies data by keywords

C.

It helps to identify the data owner

D.

It provides assurance of data integrity

Discussion
Question 19

In order to complete a major project deliverable, very specialized resources are required for some tasks. The PM failed to take into consideration during planning that the required resources would be available for fewer hours than required. Which of the following should the PM do first to make schedule changes?

Options:

A.

Add a new risk.

B.

Perform an impact analysis.

C.

Escalate to the sponsor.

D.

Raise a change request.

Discussion