Question 44

A project team has implemented a new system and needs to ensure it is usable. Which of the following should be performed first?

Options:

A.

Provide end-user training.

B.

Decommission old systems.

C.

Release external consultants.

D.

Monitor performance.

Discussion
Ace
No problem! I highly recommend Cramkey Dumps to anyone looking to pass their certification exams. They will help you feel confident and prepared on exam day. Good luck!
Harris Nov 3, 2025
That sounds amazing. I'll definitely check them out. Thanks for the recommendation!
Carson
Yeah, definitely. I would definitely recommend Cramkey Dumps to anyone who is preparing for an exam.
Rufus Nov 7, 2025
Me too. They're a lifesaver!
Vienna
I highly recommend them. They are offering exact questions that we need to prepare our exam.
Jensen Nov 1, 2025
That's great. I think I'll give Cramkey a try next time I take a certification exam. Thanks for the recommendation!
Nell
Are these dumps reliable?
Ernie Nov 23, 2025
Yes, very much so. Cramkey Dumps are created by experienced and certified professionals who have gone through the exams themselves. They understand the importance of providing accurate and relevant information to help you succeed.
Miley
Hey, I tried Cramkey Dumps for my IT certification exam. They are really awesome and helped me pass my exam with wonderful score.
Megan Nov 10, 2025
That’s great!!! I’ll definitely give it a try. Thanks!!!
Question 45

During the project execution phase, Ann, a project manager, received an email from the project sponsor asking for an additional work package to be added to the project scope due to new legislation.

INSTRUCTIONS

Review the email with the latest updates sent by the project sponsor and respond in

the following order:

1. Select the best tool for tracking the server migration progress.

2. Select the new critical path.

3. Select the correct number of engineers required for the server migration phase.

If at any time you would like to bring back the initial state of the simulation, please click

the Reset All button.

Select the Appropriate Tool:

Questions 45

Questions 45

Select the new critical path.

Option A

Option B

Option C

Questions 45

Options:

Discussion
Question 46

A project manager learns that a handful of resources from the project were pulled off the project to work on a higher priority project. The project manager had previously captured this information based on indicators of this potential change. Which of the following is the sequence of these events?

Options:

A.

Issue, issue

B.

Issue, risk

C.

Risk, issue

D.

Risk, risk

Discussion
Question 47

A team is working on a project that has different stages, such as initiation, planning, execution, and closure. Which of the following is this an example of?

Options:

A.

Agile

B.

Waterfall

C.

Standard

D.

Hybrid

Discussion