Question 20

Which of the following best describes why a project manager would decide to sign a fixed-price contract with a vendor?

Options:

A.

The scope of the project deliverable is clearly defined

B.

There is a non-disclosure agreement in place

C.

There are multiple requirements for the product

D.

The PM wants to simplify the logistics of the required product

Discussion
Question 21

An IT infrastructure change request needs to be implemented in the production environment. Which of the following elements are the most important prerequisites? (Select two).

Options:

A.

Rollback plans

B.

Project management plan

C.

Deployment plan

D.

Asset management plan

E.

Communication plan

F.

Resource management plan

Discussion
Faye
Yayyyy. I passed my exam. I think all students give these dumps a try.
Emmeline Oct 18, 2025
Definitely! I have no doubt new students will find them to be just as helpful as I did.
Rosalie
I passed. I would like to tell all students that they should definitely give Cramkey Dumps a try.
Maja Oct 23, 2025
That sounds great. I'll definitely check them out. Thanks for the suggestion!
Neve
Will I be able to achieve success after using these dumps?
Rohan Oct 9, 2025
Absolutely. It's a great way to increase your chances of success.
Cecilia
Yes, I passed my certification exam using Cramkey Dumps.
Helena Oct 16, 2025
Great. Yes they are really effective
Ace
No problem! I highly recommend Cramkey Dumps to anyone looking to pass their certification exams. They will help you feel confident and prepared on exam day. Good luck!
Harris Oct 28, 2025
That sounds amazing. I'll definitely check them out. Thanks for the recommendation!
Question 22

Which of the following aspects are true of agile as compared to waterfall? (Select two).

Options:

A.

Agile works through larger integrated teams.

B.

Agile promotes project manager ownership over deliverables.

C.

Agile reinforces the importance of comprehensive documentation.

D.

Agile has more customer involvement throughout development.

E.

Agile is more flexible to allow for changes in scope.

F.

Agile is comprised of well-defined phases.

Discussion
Question 23

A retail store is rolling out a new point-of-sale solution to several locations where the staff members normally use cash registers. Which of the following activities will best assist staff members with integrating this new solution? (Select two).

Options:

A.

Documentation

B.

Team collaboration

C.

Gap analysis

D.

Training sessions

E.

Touch points

F.

Progress monitoring

Discussion