Question 72

A project manager is taking notes along with gathering feedback about a prior project in order to consider known issues with a project enhancement. Which of the following best describes the plan that the project team is working on?

Options:

A.

A plan for capturing issues and conflicts in a project's knowledge base

B.

A plan for avoiding potential issues that may arise during project execution

C.

A plan for documenting the outcomes of the project

D.

A plan for addressing and resolving identified issues once the project has been completed

Discussion
Question 73

A project manager is in the process of evaluating the probability and impact of a risk by assigning numbers such as a monetary value. Which of the following is the project manager using?

Options:

A.

Monte Carlo simulation

B.

Root cause analysis

C.

Quantitative risk analysis

D.

Risk response analysis

Discussion
Nylah
I've been looking for good study material for my upcoming certification exam. Need help.
Dolly Oct 2, 2025
Then you should definitely give Cramkey Dumps a try. They have a huge database of questions and answers, making it easy to study and prepare for the exam. And the best part is, you can be sure the information is accurate and relevant.
Nell
Are these dumps reliable?
Ernie Oct 21, 2025
Yes, very much so. Cramkey Dumps are created by experienced and certified professionals who have gone through the exams themselves. They understand the importance of providing accurate and relevant information to help you succeed.
Vienna
I highly recommend them. They are offering exact questions that we need to prepare our exam.
Jensen Oct 11, 2025
That's great. I think I'll give Cramkey a try next time I take a certification exam. Thanks for the recommendation!
Ilyas
Definitely. I felt much more confident and prepared because of the Cramkey Dumps. I was able to answer most of the questions with ease and I think that helped me to score well on the exam.
Saoirse Oct 21, 2025
That's amazing. I'm glad you found something that worked for you. Maybe I should try them out for my next exam.
Question 74

A fix that was not submitted to the CCB for approval was applied to an application. Although the change did not have negative consequences, the sponsors expressed concern to the project manager. Which of the following should the project manager do first to prevent this situation from reoccurring?

Options:

A.

Meet with the team and highlight the importance of change management.

B.

Roll back the process and submit a change request.

C.

Document the event as a lesson learned.

D.

Remove the team member who bypassed the CCB process.

Discussion
Question 75

During the execution phase of a project, the project team faced an unexpected website downtime The project manager how a brainstorming session and the team identified causes and effects tor the problem Now the project team needs to analyze and determine whether the particular cause and effect are related by using one of the following charts. Which of the following should the team use?

A)

B)

Questions 75

C)

Questions 75

D)

Options:

A.

Option A

B.

Option B

C.

Option C

D.

Option D