Summer Special Limited Time 60% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: big60

CompTIA Updated PK0-005 Exam Questions and Answers by keyaan

Page: 18 / 28

CompTIA PK0-005 Exam Overview :

Exam Name: CompTIA Project+ Certification (2025)
Exam Code: PK0-005 Dumps
Vendor: CompTIA Certification: Project+
Questions: 386 Q&A's Shared By: keyaan
Question 72

A project manager is taking notes along with gathering feedback about a prior project in order to consider known issues with a project enhancement. Which of the following best describes the plan that the project team is working on?

Options:

A.

A plan for capturing issues and conflicts in a project's knowledge base

B.

A plan for avoiding potential issues that may arise during project execution

C.

A plan for documenting the outcomes of the project

D.

A plan for addressing and resolving identified issues once the project has been completed

Discussion
Question 73

A project manager is in the process of evaluating the probability and impact of a risk by assigning numbers such as a monetary value. Which of the following is the project manager using?

Options:

A.

Monte Carlo simulation

B.

Root cause analysis

C.

Quantitative risk analysis

D.

Risk response analysis

Discussion
Question 74

A fix that was not submitted to the CCB for approval was applied to an application. Although the change did not have negative consequences, the sponsors expressed concern to the project manager. Which of the following should the project manager do first to prevent this situation from reoccurring?

Options:

A.

Meet with the team and highlight the importance of change management.

B.

Roll back the process and submit a change request.

C.

Document the event as a lesson learned.

D.

Remove the team member who bypassed the CCB process.

Discussion
Ava-Rose
Yes! Cramkey Dumps are amazing I passed my exam…Same these questions were in exam asked.
Ismail Aug 25, 2025
Wow, that sounds really helpful. Thanks, I would definitely consider these dumps for my certification exam.
Walter
Yayyy!!! I passed my exam with the help of Cramkey Dumps. Highly appreciated!!!!
Angus Aug 25, 2025
YES….. I saw the same questions in the exam.
Nylah
I've been looking for good study material for my upcoming certification exam. Need help.
Dolly Aug 4, 2025
Then you should definitely give Cramkey Dumps a try. They have a huge database of questions and answers, making it easy to study and prepare for the exam. And the best part is, you can be sure the information is accurate and relevant.
Freddy
I passed my exam with flying colors and I'm confident who will try it surely ace the exam.
Aleksander Aug 20, 2025
Thanks for the recommendation! I'll check it out.
Alessia
Amazing Dumps. Found almost all questions in actual exam whih I prepared from these valuable dumps. Recommended!!!!
Belle Aug 27, 2025
That's impressive. I've been struggling with finding good study material for my certification. Maybe I should give Cramkey Dumps a try.
Question 75

During the execution phase of a project, the project team faced an unexpected website downtime The project manager how a brainstorming session and the team identified causes and effects tor the problem Now the project team needs to analyze and determine whether the particular cause and effect are related by using one of the following charts. Which of the following should the team use?

A)

B)

Questions 75

C)

Questions 75

D)

Options:

A.

Option A

B.

Option B

C.

Option C

D.

Option D

Discussion
Page: 18 / 28
Title
Questions
Posted

PK0-005
PDF

$42  $104.99

PK0-005 Testing Engine

$50  $124.99

PK0-005 PDF + Testing Engine

$66  $164.99