Question 72

A project manager is taking notes along with gathering feedback about a prior project in order to consider known issues with a project enhancement. Which of the following best describes the plan that the project team is working on?

Options:

A.

A plan for capturing issues and conflicts in a project's knowledge base

B.

A plan for avoiding potential issues that may arise during project execution

C.

A plan for documenting the outcomes of the project

D.

A plan for addressing and resolving identified issues once the project has been completed

Discussion
Erik
Hey, I have passed my exam using Cramkey Dumps?
Freyja Dec 14, 2025
Really, what are they? All come in your pool? Please give me more details, I am going to have access their subscription. Please brother, give me more details.
Rae
I tried using Cramkey dumps for my recent certification exam and I found them to be more accurate and up-to-date compared to other dumps I've seen. Passed the exam with wonderful score.
Rayyan Dec 16, 2025
I see your point. Thanks for sharing your thoughts. I might give it a try for my next certification exam.
Mylo
Excellent dumps with authentic information… I passed my exam with brilliant score.
Dominik Dec 26, 2025
That's amazing! I've been looking for good study material that will help me prepare for my upcoming certification exam. Now, I will try it.
Annabel
I recently used them for my exam and I passed it with excellent score. I am impressed.
Amirah Dec 3, 2025
I passed too. The questions I saw in the actual exam were exactly the same as the ones in the Cramkey Dumps. I was able to answer the questions confidently because I had already seen and studied them.
Nia
Why are these Dumps so important for students these days?
Mary Dec 19, 2025
With the constantly changing technology and advancements in the industry, it's important for students to have access to accurate and valid study material. Cramkey Dumps provide just that. They are constantly updated to reflect the latest changes and ensure that the information is up-to-date.
Question 73

A project manager is in the process of evaluating the probability and impact of a risk by assigning numbers such as a monetary value. Which of the following is the project manager using?

Options:

A.

Monte Carlo simulation

B.

Root cause analysis

C.

Quantitative risk analysis

D.

Risk response analysis

Discussion
Question 74

A fix that was not submitted to the CCB for approval was applied to an application. Although the change did not have negative consequences, the sponsors expressed concern to the project manager. Which of the following should the project manager do first to prevent this situation from reoccurring?

Options:

A.

Meet with the team and highlight the importance of change management.

B.

Roll back the process and submit a change request.

C.

Document the event as a lesson learned.

D.

Remove the team member who bypassed the CCB process.

Discussion
Question 75

During the execution phase of a project, the project team faced an unexpected website downtime The project manager how a brainstorming session and the team identified causes and effects tor the problem Now the project team needs to analyze and determine whether the particular cause and effect are related by using one of the following charts. Which of the following should the team use?

A)

B)

Questions 75

C)

Questions 75

D)

Options:

A.

Option A

B.

Option B

C.

Option C

D.

Option D

Discussion
Page: 18 / 28