Question 68

Activity resource requirements and the resource breakdown structure (RBS) are outputs of which Project Time Management process?

Options:

A.

Control Schedule

B.

Define Activities

C.

Develop Schedule

D.

Estimate Activity Resources

Discussion
Question 69

Which process includes prioritizing risks for subsequent further analysis or action by assessing and combining their probability of occurrence and impact?

Options:

A.

Perform Qualitative Risk Analysis

B.

Perform Quantitative Risk Analysis

C.

Plan Risk Management

D.

Plan Risk Responses

Discussion
Question 70

Which organizational process assets update is performed during the Close Procurements process?

Options:

A.

Procurement audit

B.

Lessons learned

C.

Performance reporting

D.

Payment requests

Discussion
Amy
I passed my exam and found your dumps 100% relevant to the actual exam.
Lacey Jan 24, 2026
Yeah, definitely. I experienced the same.
Conor
I recently used these dumps for my exam and I must say, I was impressed with their authentic material.
Yunus Jan 19, 2026
Exactly…….The information in the dumps is so authentic and up-to-date. Plus, the questions are very similar to what you'll see on the actual exam. I felt confident going into the exam because I had studied using Cramkey Dumps.
Sarah
Yeah, I was so relieved when I saw that the question appeared in the exam were similar to their exam dumps. It made the exam a lot easier and I felt confident going into it.
Aaliyah Jan 20, 2026
Same here. I've heard mixed reviews about using exam dumps, but for us, it definitely paid off.
Andrew
Are these dumps helpful?
Jeremiah Jan 19, 2026
Yes, Don’t worry!!! I'm confident you'll find them to be just as helpful as I did. Good luck with your exam!
Question 71

What is the name of a graphic display of project team members and their reporting relationships?

Options:

A.

Role dependencies chart

B.

Reporting flow diagram

C.

Project organization chart

D.

Project team structure diagram

Discussion
Page: 17 / 26
Title
Questions
Posted

PMI-100
PDF

$36.75  $104.99

PMI-100 Testing Engine

$43.75  $124.99

PMI-100 PDF + Testing Engine

$57.75  $164.99