PMI Updated PMI-100 Exam Questions and Answers by nour

Page: 11 / 26

PMI PMI-100 Exam Overview :

Exam Name: Certified Associate in Project Management (CAPM)®
Exam Code: PMI-100 Dumps
Vendor: PMI Certification: CAPM
Questions: 704 Q&A's Shared By: nour
Question 44

Which of the following is an example of schedule compression?

Options:

A.

Activity sequencing

B.

Resource leveling

C.

Lead and lag adjusting

D.

Crashing

Discussion
Annabel
I recently used them for my exam and I passed it with excellent score. I am impressed.
Amirah Oct 27, 2025
I passed too. The questions I saw in the actual exam were exactly the same as the ones in the Cramkey Dumps. I was able to answer the questions confidently because I had already seen and studied them.
Andrew
Are these dumps helpful?
Jeremiah Oct 2, 2025
Yes, Don’t worry!!! I'm confident you'll find them to be just as helpful as I did. Good luck with your exam!
Hassan
Highly Recommended Dumps… today I passed my exam! Same questions appear. I bought Full Access.
Kasper Oct 17, 2025
Hey wonderful….so same questions , sounds good. Planning to write this week, I will go for full access today.
Georgina
I used Cramkey Dumps to prepare for my recent exam and I have to say, they were a huge help.
Corey Oct 25, 2025
Really? How did they help you? I know these are the same questions appears in exam. I will give my try. But tell me if they also help in some training?
Lennox
Something Special that they provide a comprehensive overview of the exam content. They cover all the important topics and concepts, so you can be confident that you are well-prepared for the test.
Aiza Oct 12, 2025
That makes sense. What makes Cramkey Dumps different from other study materials?
Question 45

In Project Cost Management, which input is exclusive to the Determine Budget process?

Options:

A.

Scope baseline

B.

Organizational process assets

C.

Project schedule

D.

Resource calendars

Discussion
Question 46

The key benefit of the Monitoring and Controlling Process Group is the ability to:

Options:

A.

establish and manage project communication channels, both external and internal to the project team.

B.

influence the stakeholders that want to circumvent integrated change control so that their changes are implemented.

C.

monitor the ongoing project team against the team performance assessments and the project performance baseline.

D.

observe and measure project performance regularly and consistently to identify variances from the project management plan.

Discussion
Question 47

As the project progresses, which of the following is routinely collected from the project activities?

Options:

A.

Communication management activities

B.

Change requests

C.

Configuration verification and audit

D.

Work performance information

Discussion