Question 44

Which of the following is an example of schedule compression?

Options:

A.

Activity sequencing

B.

Resource leveling

C.

Lead and lag adjusting

D.

Crashing

Discussion
Nadia
Why these dumps are important? Can I pass my exam without these dumps?
Julian Oct 19, 2025
The questions in the Cramkey dumps are explained in detail and there are also study notes and reference materials provided. This made it easier for me to understand the concepts and retain the information better.
Norah
Cramkey is highly recommended.
Zayan Oct 19, 2025
Definitely. If you're looking for a reliable and effective study resource, look no further than Cramkey Dumps. They're simply wonderful!
Ella-Rose
Amazing website with excellent Dumps. I passed my exam and secured excellent marks!!!
Alisha Oct 2, 2025
Extremely accurate. They constantly update their materials with the latest exam questions and answers, so you can be confident that what you're studying is up-to-date.
Alessia
Amazing Dumps. Found almost all questions in actual exam whih I prepared from these valuable dumps. Recommended!!!!
Belle Oct 26, 2025
That's impressive. I've been struggling with finding good study material for my certification. Maybe I should give Cramkey Dumps a try.
Question 45

In Project Cost Management, which input is exclusive to the Determine Budget process?

Options:

A.

Scope baseline

B.

Organizational process assets

C.

Project schedule

D.

Resource calendars

Discussion
Question 46

The key benefit of the Monitoring and Controlling Process Group is the ability to:

Options:

A.

establish and manage project communication channels, both external and internal to the project team.

B.

influence the stakeholders that want to circumvent integrated change control so that their changes are implemented.

C.

monitor the ongoing project team against the team performance assessments and the project performance baseline.

D.

observe and measure project performance regularly and consistently to identify variances from the project management plan.

Discussion
Question 47

As the project progresses, which of the following is routinely collected from the project activities?

Options:

A.

Communication management activities

B.

Change requests

C.

Configuration verification and audit

D.

Work performance information

Discussion