Question 48

When large or complex projects are separated into distinct phases or subprojects, all of the Process Groups would normally be:

Options:

A.

divided among each of the phases or subprojects.

B.

repeated for each of the phases or subprojects.

C.

linked to specific phases or subprojects.

D.

integrated for specific phases or subprojects.

Discussion
Ivan
I tried these dumps for my recent certification exam and I found it pretty helpful.
Elis Jan 12, 2026
Agree!!! The questions in the dumps were quite similar to what came up in the actual exam. It gave me a good idea of the types of questions to expect and helped me revise efficiently.
Walter
Yayyy!!! I passed my exam with the help of Cramkey Dumps. Highly appreciated!!!!
Angus Jan 15, 2026
YES….. I saw the same questions in the exam.
Nia
Why are these Dumps so important for students these days?
Mary Jan 18, 2026
With the constantly changing technology and advancements in the industry, it's important for students to have access to accurate and valid study material. Cramkey Dumps provide just that. They are constantly updated to reflect the latest changes and ensure that the information is up-to-date.
Nell
Are these dumps reliable?
Ernie Jan 20, 2026
Yes, very much so. Cramkey Dumps are created by experienced and certified professionals who have gone through the exams themselves. They understand the importance of providing accurate and relevant information to help you succeed.
Question 49

The milestone list is an input to which process from the Planning Process Group?

Options:

A.

Define Activities

B.

Estimate Activity Durations

C.

Estimate Activity Resources

D.

Sequence Activities

Discussion
Question 50

The purpose of inspection in Perform Quality Control is to keep errors:

Options:

A.

in line with a measured degree of conformity.

B.

out of the hands of the customer.

C.

in a specified range of acceptable results.

D.

out of the process.

Discussion
Question 51

In which Project Management Process Group is the project charter developed?

Options:

A.

Monitoring and Controlling

B.

Executing

C.

Initiating

D.

Planning

Discussion
Page: 12 / 26
Title
Questions
Posted

PMI-100
PDF

$36.75  $104.99

PMI-100 Testing Engine

$43.75  $124.99

PMI-100 PDF + Testing Engine

$57.75  $164.99