Question 48

When large or complex projects are separated into distinct phases or subprojects, all of the Process Groups would normally be:

Options:

A.

divided among each of the phases or subprojects.

B.

repeated for each of the phases or subprojects.

C.

linked to specific phases or subprojects.

D.

integrated for specific phases or subprojects.

Discussion
Melody
My experience with Cramkey was great! I was surprised to see that many of the questions in my exam appeared in the Cramkey dumps.
Colby Aug 26, 2025
Yes, In fact, I got a score of above 85%. And I attribute a lot of my success to Cramkey's dumps.
Alaia
These Dumps are amazing! I used them to study for my recent exam and I passed with flying colors. The information in the dumps is so valid and up-to-date. Thanks a lot!!!
Zofia Aug 20, 2025
That's great to hear! I've been struggling to find good study material for my exam. I will ty it for sure.
Atlas
What are these Dumps? Would anybody please explain it to me.
Reign Aug 9, 2025
These are exam dumps for a variety of IT certifications. They have a vast collection of updated questions and answers, which are very helpful in preparing for the exams.
Josephine
I want to ask about their study material and Customer support? Can anybody guide me?
Zayd Aug 1, 2025
Yes, the dumps or study material provided by them are authentic and up to date. They have a dedicated team to assist students and make sure they have a positive experience.
Faye
Yayyyy. I passed my exam. I think all students give these dumps a try.
Emmeline Aug 14, 2025
Definitely! I have no doubt new students will find them to be just as helpful as I did.
Question 49

The milestone list is an input to which process from the Planning Process Group?

Options:

A.

Define Activities

B.

Estimate Activity Durations

C.

Estimate Activity Resources

D.

Sequence Activities

Discussion
Question 50

The purpose of inspection in Perform Quality Control is to keep errors:

Options:

A.

in line with a measured degree of conformity.

B.

out of the hands of the customer.

C.

in a specified range of acceptable results.

D.

out of the process.

Discussion
Question 51

In which Project Management Process Group is the project charter developed?

Options:

A.

Monitoring and Controlling

B.

Executing

C.

Initiating

D.

Planning

Discussion