Question 60

A project has a current cost performance index (CPI) of 1.25. To date, US$10,000 have been spent on performing the project work. What is the earned value of the work completed to date?

Options:

A.

US$S000

B.

US$9500

C.

US$10,000

D.

US$12,500

Discussion
Miriam
Highly recommended Dumps. 100% authentic and reliable. Passed my exam with wonderful score.
Milan Jan 12, 2026
I see. Thanks for the information. I'll definitely keep Cramkey in mind for my next exam.
Ari
Can anyone explain what are these exam dumps and how are they?
Ocean Jan 4, 2026
They're exam preparation materials that are designed to help you prepare for various certification exams. They provide you with up-to-date and accurate information to help you pass your exams.
Yusra
I passed my exam. Cramkey Dumps provides detailed explanations for each question and answer, so you can understand the concepts better.
Alisha Jan 26, 2026
I recently used their dumps for the certification exam I took and I have to say, I was really impressed.
Ilyas
Definitely. I felt much more confident and prepared because of the Cramkey Dumps. I was able to answer most of the questions with ease and I think that helped me to score well on the exam.
Saoirse Jan 14, 2026
That's amazing. I'm glad you found something that worked for you. Maybe I should try them out for my next exam.
Esmae
I highly recommend Cramkey Dumps to anyone preparing for the certification exam.
Mollie Jan 13, 2026
Absolutely. They really make it easier to study and retain all the important information. I'm so glad I found Cramkey Dumps.
Question 61

Which of the following is the primary output of the Identify Risks process?

Options:

A.

Risk management plan

B.

Risk register

C.

Change requests

D.

Risk response plan

Discussion
Question 62

Which standard has interrelationships to other project management disciplines such as program management and portfolio management?

Options:

A.

Program Management Body of Knowledge Guide

B.

The Standard for Program Management

C.

Organizational Project Management Maturity Model (OPM3$)

D.

Guide to the Project Management Body of Knowledge (PMBOK®)

Discussion
Question 63

Another name for an Ishikawa diagram is:

Options:

A.

cause and effect diagram.

B.

control chart.

C.

flowchart.

D.

histogram.

Discussion