PMI Updated PMI-100 Exam Questions and Answers by laurie

Page: 15 / 26

PMI PMI-100 Exam Overview :

Exam Name: Certified Associate in Project Management (CAPM)®
Exam Code: PMI-100 Dumps
Vendor: PMI Certification: CAPM
Questions: 704 Q&A's Shared By: laurie
Question 60

A project has a current cost performance index (CPI) of 1.25. To date, US$10,000 have been spent on performing the project work. What is the earned value of the work completed to date?

Options:

A.

US$S000

B.

US$9500

C.

US$10,000

D.

US$12,500

Discussion
Question 61

Which of the following is the primary output of the Identify Risks process?

Options:

A.

Risk management plan

B.

Risk register

C.

Change requests

D.

Risk response plan

Discussion
Question 62

Which standard has interrelationships to other project management disciplines such as program management and portfolio management?

Options:

A.

Program Management Body of Knowledge Guide

B.

The Standard for Program Management

C.

Organizational Project Management Maturity Model (OPM3$)

D.

Guide to the Project Management Body of Knowledge (PMBOK®)

Discussion
Everleigh
I must say that they are updated regularly to reflect the latest exam content, so you can be sure that you are getting the most accurate information. Plus, they are easy to use and understand, so even new students can benefit from them.
Huxley Oct 10, 2025
That's great to know. So, you think new students should buy these dumps?
Rae
I tried using Cramkey dumps for my recent certification exam and I found them to be more accurate and up-to-date compared to other dumps I've seen. Passed the exam with wonderful score.
Rayyan Oct 3, 2025
I see your point. Thanks for sharing your thoughts. I might give it a try for my next certification exam.
Kylo
What makes Cramkey Dumps so reliable? Please guide.
Sami Oct 25, 2025
Well, for starters, they have a team of experts who are constantly updating their material to reflect the latest changes in the industry. Plus, they have a huge database of questions and answers, which makes it easy to study and prepare for the exam.
Ernest
That's amazing. I think I'm going to give Cramkey Dumps a try for my next exam. Thanks for telling me about them! CramKey admin please share more questions……You guys are amazing.
Nate Oct 6, 2025
I failed last week, I never know this site , but amazed to see all these questions were in my exam week before. I feel bad now, why I didn’t bother this site. Thanks Cramkey, Excellent Job.
Question 63

Another name for an Ishikawa diagram is:

Options:

A.

cause and effect diagram.

B.

control chart.

C.

flowchart.

D.

histogram.

Discussion
Page: 15 / 26
Title
Questions
Posted

PMI-100
PDF

$36.75  $104.99

PMI-100 Testing Engine

$43.75  $124.99

PMI-100 PDF + Testing Engine

$57.75  $164.99