New Year Sale Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: get65

PMI Updated PMI-100 Exam Questions and Answers by laurie

Page: 15 / 26

PMI PMI-100 Exam Overview :

Exam Name: Certified Associate in Project Management (CAPM)®
Exam Code: PMI-100 Dumps
Vendor: PMI Certification: CAPM
Questions: 704 Q&A's Shared By: laurie
Question 60

A project has a current cost performance index (CPI) of 1.25. To date, US$10,000 have been spent on performing the project work. What is the earned value of the work completed to date?

Options:

A.

US$S000

B.

US$9500

C.

US$10,000

D.

US$12,500

Discussion
Ayra
How these dumps are necessary for passing the certification exam?
Damian Nov 14, 2025
They give you a competitive edge and help you prepare better.
Kylo
What makes Cramkey Dumps so reliable? Please guide.
Sami Nov 2, 2025
Well, for starters, they have a team of experts who are constantly updating their material to reflect the latest changes in the industry. Plus, they have a huge database of questions and answers, which makes it easy to study and prepare for the exam.
Lois
I passed my exam with wonderful score. Their dumps are 100% valid and I felt confident during the exam.
Ernie Nov 2, 2025
Absolutely. The best part is, the answers in the dumps were correct. So, I felt confident and well-prepared for the exam.
Honey
I highly recommend it. They made a big difference for me and I'm sure they'll help you too. Just make sure to use them wisely and not solely rely on them. They should be used as a supplement to your regular studies.
Antoni Nov 12, 2025
Good point. Thanks for the advice. I'll definitely keep that in mind.
Question 61

Which of the following is the primary output of the Identify Risks process?

Options:

A.

Risk management plan

B.

Risk register

C.

Change requests

D.

Risk response plan

Discussion
Question 62

Which standard has interrelationships to other project management disciplines such as program management and portfolio management?

Options:

A.

Program Management Body of Knowledge Guide

B.

The Standard for Program Management

C.

Organizational Project Management Maturity Model (OPM3$)

D.

Guide to the Project Management Body of Knowledge (PMBOK®)

Discussion
Question 63

Another name for an Ishikawa diagram is:

Options:

A.

cause and effect diagram.

B.

control chart.

C.

flowchart.

D.

histogram.

Discussion
Page: 15 / 26
Title
Questions
Posted

PMI-100
PDF

$36.75  $104.99

PMI-100 Testing Engine

$43.75  $124.99

PMI-100 PDF + Testing Engine

$57.75  $164.99