Question 60

A project has a current cost performance index (CPI) of 1.25. To date, US$10,000 have been spent on performing the project work. What is the earned value of the work completed to date?

Options:

A.

US$S000

B.

US$9500

C.

US$10,000

D.

US$12,500

Discussion
Billy
It was like deja vu! I was confident going into the exam because I had already seen those questions before.
Vincent Jan 26, 2026
Definitely. And the best part is, I passed! I feel like all that hard work and preparation paid off. Cramkey is the best resource for all students!!!
Aryan
Absolutely rocked! They are an excellent investment for anyone who wants to pass the exam on the first try. They save you time and effort by providing a comprehensive overview of the exam content, and they give you a competitive edge by giving you access to the latest information. So, I definitely recommend them to new students.
Jessie Jan 17, 2026
did you use PDF or Engine? Which one is most useful?
Mariam
Do anyone think Cramkey questions can help improve exam scores?
Katie Jan 19, 2026
Absolutely! Many people have reported improved scores after using Cramkey Dumps, and there are also success stories of people passing exams on the first try. I already passed this exam. I confirmed above questions were in exam.
Nadia
Why these dumps are important? Can I pass my exam without these dumps?
Julian Jan 19, 2026
The questions in the Cramkey dumps are explained in detail and there are also study notes and reference materials provided. This made it easier for me to understand the concepts and retain the information better.
Question 61

Which of the following is the primary output of the Identify Risks process?

Options:

A.

Risk management plan

B.

Risk register

C.

Change requests

D.

Risk response plan

Discussion
Question 62

Which standard has interrelationships to other project management disciplines such as program management and portfolio management?

Options:

A.

Program Management Body of Knowledge Guide

B.

The Standard for Program Management

C.

Organizational Project Management Maturity Model (OPM3$)

D.

Guide to the Project Management Body of Knowledge (PMBOK®)

Discussion
Question 63

Another name for an Ishikawa diagram is:

Options:

A.

cause and effect diagram.

B.

control chart.

C.

flowchart.

D.

histogram.

Discussion