Question 24

Which input to the Manage Stakeholder Engagement process is used to document changes that occur during the project?

Options:

A.

Issue log

B.

Change log

C.

Expert judgment

D.

Change requests

Discussion
Aryan
Absolutely rocked! They are an excellent investment for anyone who wants to pass the exam on the first try. They save you time and effort by providing a comprehensive overview of the exam content, and they give you a competitive edge by giving you access to the latest information. So, I definitely recommend them to new students.
Jessie Aug 24, 2025
did you use PDF or Engine? Which one is most useful?
Josie
I just passed my certification exam using their dumps and I must say, I was thoroughly impressed.
Fatimah Aug 14, 2025
You’re right. The dumps were authentic and covered all the important topics. I felt confident going into the exam and it paid off.
Pippa
I was so happy to see that almost all the questions on the exam were exactly what I found in their Dumps.
Anastasia Aug 27, 2025
You are right…It was amazing! The Cramkey Dumps were so comprehensive and well-organized, it made studying for the exam a breeze.
Amy
I passed my exam and found your dumps 100% relevant to the actual exam.
Lacey Aug 17, 2025
Yeah, definitely. I experienced the same.
Osian
Dumps are fantastic! I recently passed my certification exam using these dumps and I must say, they are 100% valid.
Azaan Aug 26, 2025
They are incredibly accurate and valid. I felt confident going into my exam because the dumps covered all the important topics and the questions were very similar to what I saw on the actual exam. The team of experts behind Cramkey Dumps make sure the information is relevant and up-to-date.
Question 25

Which tool or technique is used in the Develop Project Management Plan process?

Options:

A.

Pareto diagram

B.

Performance reporting

C.

SWOT analysis

D.

Expert judgment

Discussion
Question 26

An input to the Plan Procurement Management process is:

Options:

A.

Source selection criteria.

B.

Market research.

C.

A stakeholder register.

D.

A records management system.

Discussion
Question 27

When a backward pass is calculated from a schedule constraint that is later than the early finish date that has been calculated during a forward pass calculation, this causes which type of total float?

Options:

A.

Negative

B.

Zero

C.

Positive

D.

Free

Discussion
Page: 6 / 26
Title
Questions
Posted

PMI-100
PDF

$42  $104.99

PMI-100 Testing Engine

$50  $124.99

PMI-100 PDF + Testing Engine

$66  $164.99