Question 96

Stakeholder communication requirements should be included as a component of:

Options:

A.

enterprise environmental factors

B.

organizational process assets

C.

the project management plan

D.

the stakeholder register

Discussion
Hendrix
Great website with Great Exam Dumps. Just passed my exam today.
Luka Oct 7, 2025
Absolutely. Cramkey Dumps only provides the latest and most updated exam questions and answers.
Cody
I used Cramkey Dumps to prepare and a lot of the questions on the exam were exactly what I found in their study materials.
Eric Oct 26, 2025
Really? That's great to hear! I used Cramkey Dumps too and I had the same experience. The questions were almost identical.
Walter
Yayyy!!! I passed my exam with the help of Cramkey Dumps. Highly appreciated!!!!
Angus Oct 14, 2025
YES….. I saw the same questions in the exam.
Victoria
Hey, guess what? I passed the certification exam! I couldn't have done it without Cramkey Dumps.
Isabel Oct 17, 2025
Same here! I was so surprised when I saw that almost all the questions on the exam were exactly what I found in their study materials.
Honey
I highly recommend it. They made a big difference for me and I'm sure they'll help you too. Just make sure to use them wisely and not solely rely on them. They should be used as a supplement to your regular studies.
Antoni Oct 16, 2025
Good point. Thanks for the advice. I'll definitely keep that in mind.
Question 97

A project team member agrees to change a project deliverable after a conversation with an external stakeholder. It is later discovered that the change has had an adverse effect on another deliverable. This could have been avoided if the project team had implemented:

Options:

A.

Quality assurance.

B.

A stakeholder management plan.

C.

Project team building.

D.

Integrated change control.

Discussion
Question 98

The following chart contains information about the tasks in a project.

Questions 98

Based on the chart, what is the cost performance index (CPI) for Task 2?

Options:

A.

0.8

B.

1

C.

1.25

D.

1.8

Discussion
Question 99

Technical capability, past performance, and intellectual property rights are examples of:

Options:

A.

performance measurement criteria

B.

source selection criteria

C.

product acceptance criteria

D.

phase exit criteria

Discussion