New Year Sale Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: get65

PMI Updated PMI-100 Exam Questions and Answers by emmanuel

Page: 24 / 26

PMI PMI-100 Exam Overview :

Exam Name: Certified Associate in Project Management (CAPM)®
Exam Code: PMI-100 Dumps
Vendor: PMI Certification: CAPM
Questions: 704 Q&A's Shared By: emmanuel
Question 96

Stakeholder communication requirements should be included as a component of:

Options:

A.

enterprise environmental factors

B.

organizational process assets

C.

the project management plan

D.

the stakeholder register

Discussion
Question 97

A project team member agrees to change a project deliverable after a conversation with an external stakeholder. It is later discovered that the change has had an adverse effect on another deliverable. This could have been avoided if the project team had implemented:

Options:

A.

Quality assurance.

B.

A stakeholder management plan.

C.

Project team building.

D.

Integrated change control.

Discussion
Ayra
How these dumps are necessary for passing the certification exam?
Damian Nov 14, 2025
They give you a competitive edge and help you prepare better.
Aliza
I used these dumps for my recent certification exam and I can say with certainty that they're absolutely valid dumps. The questions were very similar to what came up in the actual exam.
Jakub Nov 11, 2025
That's great to hear. I am going to try them soon.
Freddy
I passed my exam with flying colors and I'm confident who will try it surely ace the exam.
Aleksander Nov 26, 2025
Thanks for the recommendation! I'll check it out.
Victoria
Hey, guess what? I passed the certification exam! I couldn't have done it without Cramkey Dumps.
Isabel Nov 25, 2025
Same here! I was so surprised when I saw that almost all the questions on the exam were exactly what I found in their study materials.
Question 98

The following chart contains information about the tasks in a project.

Questions 98

Based on the chart, what is the cost performance index (CPI) for Task 2?

Options:

A.

0.8

B.

1

C.

1.25

D.

1.8

Discussion
Question 99

Technical capability, past performance, and intellectual property rights are examples of:

Options:

A.

performance measurement criteria

B.

source selection criteria

C.

product acceptance criteria

D.

phase exit criteria

Discussion
Page: 24 / 26
Title
Questions
Posted

PMI-100
PDF

$36.75  $104.99

PMI-100 Testing Engine

$43.75  $124.99

PMI-100 PDF + Testing Engine

$57.75  $164.99