Question 8

Who is responsible for initiating a project?

Options:

A.

Project sponsor

B.

Project manager

C.

Program manager

D.

Project management office (PMO)

Discussion
Annabel
I recently used them for my exam and I passed it with excellent score. I am impressed.
Amirah Sep 10, 2025
I passed too. The questions I saw in the actual exam were exactly the same as the ones in the Cramkey Dumps. I was able to answer the questions confidently because I had already seen and studied them.
Pippa
I was so happy to see that almost all the questions on the exam were exactly what I found in their Dumps.
Anastasia Sep 17, 2025
You are right…It was amazing! The Cramkey Dumps were so comprehensive and well-organized, it made studying for the exam a breeze.
Hassan
Highly Recommended Dumps… today I passed my exam! Same questions appear. I bought Full Access.
Kasper Sep 11, 2025
Hey wonderful….so same questions , sounds good. Planning to write this week, I will go for full access today.
Wyatt
Passed my exam… Thank you so much for your excellent Exam Dumps.
Arjun Sep 26, 2025
That sounds really useful. I'll definitely check it out.
Question 9

The process of identifying specific actions to be performed to produce project deliverables is:

Options:

A.

Define Activities.

B.

Create WBS.

C.

Define Scope.

D.

Develop Schedule.

Discussion
Question 10

An input to the Estimate Activity Resources process is:

Options:

A.

Activity resource requirements.

B.

Published estimating data.

C.

Resource calendars.

D.

Resource breakdown structure (RBS).

Discussion
Question 11

Which of the following is an output of Close Procurements?

Options:

A.

Accepted deliverables

B.

Organizational process assets updates

C.

Managing stakeholder expectations

D.

Performance reports

Discussion