Question 52

In which process is a project manager identified and given the authority to apply resources to project activities?

Options:

A.

Acquire Project Team

B.

Develop Project Management Plan

C.

Manage Project Execution

D.

Develop Project Charter

Discussion
Alaia
These Dumps are amazing! I used them to study for my recent exam and I passed with flying colors. The information in the dumps is so valid and up-to-date. Thanks a lot!!!
Zofia Oct 13, 2025
That's great to hear! I've been struggling to find good study material for my exam. I will ty it for sure.
Nia
Why are these Dumps so important for students these days?
Mary Oct 20, 2025
With the constantly changing technology and advancements in the industry, it's important for students to have access to accurate and valid study material. Cramkey Dumps provide just that. They are constantly updated to reflect the latest changes and ensure that the information is up-to-date.
Reeva
Wow what a success I achieved today. Thank you so much Cramkey for amazing Dumps. All students must try it.
Amari Oct 13, 2025
Wow, that's impressive. I'll definitely keep Cramkey in mind for my next exam.
Syeda
I passed, Thank you Cramkey for your precious Dumps.
Stella Oct 15, 2025
That's great. I think I'll give Cramkey Dumps a try.
Ace
No problem! I highly recommend Cramkey Dumps to anyone looking to pass their certification exams. They will help you feel confident and prepared on exam day. Good luck!
Harris Oct 28, 2025
That sounds amazing. I'll definitely check them out. Thanks for the recommendation!
Question 53

Which of the following statements is true regarding project and product lifecycles?

Options:

A.

A single product lifecycle may consist of multiple project lifecycles.

B.

A product lifecycle is always shorter than the project lifecycle.

C.

A single product lifecycle can only have one project lifecycle.

D.

A single project lifecycle may consist of multiple product lifecycles.

Discussion
Question 54

Based on the following metrics: EV= $20,000, AC= $22,000, and PV= $28,000, what is the project CV?

Options:

A.

-8000

B.

-2000

C.

2000

D.

8000

Discussion
Question 55

The PV is $1000, EV is $2000, and AC is $1500. What is CPI?

Options:

A.

1.33

B.

2

C.

0.75

D.

0.5

Discussion