Independence Day Special Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: get65

PMI Updated PMI-100 Exam Questions and Answers by gaia

Page: 10 / 26

PMI PMI-100 Exam Overview :

Exam Name: Certified Associate in Project Management (CAPM)®
Exam Code: PMI-100 Dumps
Vendor: PMI Certification: CAPM
Questions: 704 Q&A's Shared By: gaia
Question 40

Which process involves monitoring the status of the project to update the project costs and managing changes to the cost baseline?

Options:

A.

Estimate Costs

B.

Control Costs

C.

Determine Budget

D.

Plan Cost Management

Discussion
Lennox
Something Special that they provide a comprehensive overview of the exam content. They cover all the important topics and concepts, so you can be confident that you are well-prepared for the test.
Aiza (not set)
That makes sense. What makes Cramkey Dumps different from other study materials?
Fatima
Hey I passed my exam. The world needs to know about it. I have never seen real exam questions on any other exam preparation resource like I saw on Cramkey Dumps.
Niamh (not set)
That's true. Cramkey Dumps are simply the best when it comes to preparing for the certification exam. They have all the key information you need and the questions are very similar to what you'll see on the actual exam.
Laila
They're such a great resource for anyone who wants to improve their exam results. I used these dumps and passed my exam!! Happy customer, always prefer. Yes, same questions as above I know you guys are perfect.
Keira (not set)
100% right….And they're so affordable too. It's amazing how much value you get for the price.
Josephine
I want to ask about their study material and Customer support? Can anybody guide me?
Zayd (not set)
Yes, the dumps or study material provided by them are authentic and up to date. They have a dedicated team to assist students and make sure they have a positive experience.
Question 41

What is the estimate at completion (EAC) if the budget at completion (BAC) is $100, the actual cost (AC) is $50, and the earned value (EV) is $25?

Options:

A.

$50

B.

$100

C.

$125

D.

$175

Discussion
Question 42

An output of the Manage Stakeholder Engagement process is:

Options:

A.

change requests

B.

enterprise environmental factors

C.

the stakeholder management plan

D.

the change log

Discussion
Question 43

Which type of analysis is used as a general management technique within the Plan Procurements process?

Options:

A.

Risk assessment analysis

B.

Make or buy analysis

C.

Contract value analysis

D.

Cost impact analysis

Discussion
Page: 10 / 26
Title
Questions
Posted

PMI-100
PDF

$35  $99.99

PMI-100 Testing Engine

$42  $119.99

PMI-100 PDF + Testing Engine

$56  $159.99