Question 92

The component of the human resource management plan that includes ways in which team members can obtain certifications that support their ability to benefit the project is known as:

Options:

A.

recognition and rewards

B.

compliance

C.

staff acquisition

D.

training needs

Discussion
Nell
Are these dumps reliable?
Ernie (not set)
Yes, very much so. Cramkey Dumps are created by experienced and certified professionals who have gone through the exams themselves. They understand the importance of providing accurate and relevant information to help you succeed.
Mylo
Excellent dumps with authentic information… I passed my exam with brilliant score.
Dominik (not set)
That's amazing! I've been looking for good study material that will help me prepare for my upcoming certification exam. Now, I will try it.
Kingsley
Do anyone guide my how these dumps would be helpful for new students like me?
Haris (not set)
Absolutely! They are highly recommended for anyone looking to pass their certification exam. The dumps are easy to understand and follow, making it easier for you to study and retain the information.
Norah
Cramkey is highly recommended.
Zayan (not set)
Definitely. If you're looking for a reliable and effective study resource, look no further than Cramkey Dumps. They're simply wonderful!
Kylo
What makes Cramkey Dumps so reliable? Please guide.
Sami (not set)
Well, for starters, they have a team of experts who are constantly updating their material to reflect the latest changes in the industry. Plus, they have a huge database of questions and answers, which makes it easy to study and prepare for the exam.
Question 93

The following is a network diagram for a project.

Questions 93

What is the critical path for the project?

Options:

A.

A-B-D-G

B.

A-B-E-G

C.

A-C-F-G

D.

A-C-E-G

Discussion
Question 94

Which tool or technique used in the Control Procurements process can be conducted during the execution of the project to verify compliance with deliverables?

Options:

A.

Procurement documents

B.

Inspection and audits

C.

Estimate budget

D.

Risk register

Discussion
Question 95

Which Perform Quality Assurance tool or technique is used to identify a problem, discover the underlying causes that lead to it, and develop preventative actions?

Options:

A.

Inspection

B.

Quality audits

C.

Design of experiments

D.

Root cause analysis

Discussion