Question 92

The component of the human resource management plan that includes ways in which team members can obtain certifications that support their ability to benefit the project is known as:

Options:

A.

recognition and rewards

B.

compliance

C.

staff acquisition

D.

training needs

Discussion
Ari
Can anyone explain what are these exam dumps and how are they?
Ocean (not set)
They're exam preparation materials that are designed to help you prepare for various certification exams. They provide you with up-to-date and accurate information to help you pass your exams.
Atlas
What are these Dumps? Would anybody please explain it to me.
Reign (not set)
These are exam dumps for a variety of IT certifications. They have a vast collection of updated questions and answers, which are very helpful in preparing for the exams.
Neve
Will I be able to achieve success after using these dumps?
Rohan (not set)
Absolutely. It's a great way to increase your chances of success.
Sarah
Yeah, I was so relieved when I saw that the question appeared in the exam were similar to their exam dumps. It made the exam a lot easier and I felt confident going into it.
Aaliyah (not set)
Same here. I've heard mixed reviews about using exam dumps, but for us, it definitely paid off.
Josie
I just passed my certification exam using their dumps and I must say, I was thoroughly impressed.
Fatimah (not set)
You’re right. The dumps were authentic and covered all the important topics. I felt confident going into the exam and it paid off.
Question 93

The following is a network diagram for a project.

Questions 93

What is the critical path for the project?

Options:

A.

A-B-D-G

B.

A-B-E-G

C.

A-C-F-G

D.

A-C-E-G

Discussion
Question 94

Which tool or technique used in the Control Procurements process can be conducted during the execution of the project to verify compliance with deliverables?

Options:

A.

Procurement documents

B.

Inspection and audits

C.

Estimate budget

D.

Risk register

Discussion
Question 95

Which Perform Quality Assurance tool or technique is used to identify a problem, discover the underlying causes that lead to it, and develop preventative actions?

Options:

A.

Inspection

B.

Quality audits

C.

Design of experiments

D.

Root cause analysis

Discussion