Question 20

Which type of dependency is contractually required or inherent in the nature of the work?

Options:

A.

External

B.

Lead

C.

Discretionary

D.

Mandatory

Discussion
Ilyas
Definitely. I felt much more confident and prepared because of the Cramkey Dumps. I was able to answer most of the questions with ease and I think that helped me to score well on the exam.
Saoirse Sep 25, 2024
That's amazing. I'm glad you found something that worked for you. Maybe I should try them out for my next exam.
Alaya
Best Dumps among other dumps providers. I like it so much because of their authenticity.
Kaiden Sep 16, 2024
That's great. I've used other dump providers in the past and they were often outdated or had incorrect information. This time I will try it.
Neve
Will I be able to achieve success after using these dumps?
Rohan Oct 24, 2024
Absolutely. It's a great way to increase your chances of success.
Esmae
I highly recommend Cramkey Dumps to anyone preparing for the certification exam.
Mollie Aug 15, 2024
Absolutely. They really make it easier to study and retain all the important information. I'm so glad I found Cramkey Dumps.
Question 21

Who determines which dependencies are mandatory during the Sequence Activities process?

Options:

A.

Project manager

B.

External stakeholders

C.

Internal stakeholders

D.

Project team

Discussion
Question 22

Which input to Collect Requirements is used to identify stakeholders who can provide information on requirements?

Options:

A.

Stakeholder register

B.

Scope management plan

C.

Stakeholder management plan

D.

Project charter

Discussion
Question 23

The Plan Stakeholder Management process belongs to which Process Group?

Options:

A.

Executing

B.

Initiating

C.

Planning

D.

Monitoring and Controlling

Discussion