Question 20

Which type of dependency is contractually required or inherent in the nature of the work?

Options:

A.

External

B.

Lead

C.

Discretionary

D.

Mandatory

Discussion
Question 21

Who determines which dependencies are mandatory during the Sequence Activities process?

Options:

A.

Project manager

B.

External stakeholders

C.

Internal stakeholders

D.

Project team

Discussion
Question 22

Which input to Collect Requirements is used to identify stakeholders who can provide information on requirements?

Options:

A.

Stakeholder register

B.

Scope management plan

C.

Stakeholder management plan

D.

Project charter

Discussion
Hendrix
Great website with Great Exam Dumps. Just passed my exam today.
Luka Aug 31, 2024
Absolutely. Cramkey Dumps only provides the latest and most updated exam questions and answers.
Peyton
Hey guys. Guess what? I passed my exam. Thanks a lot Cramkey, your provided information was relevant and reliable.
Coby Sep 6, 2024
Thanks for sharing your experience. I think I'll give Cramkey a try for my next exam.
Teddie
yes, I passed my exam with wonderful score, Accurate and valid dumps.
Isla-Rose Aug 18, 2024
Absolutely! The questions in the dumps were almost identical to the ones that appeared in the actual exam. I was able to answer almost all of them correctly.
Rosalie
I passed. I would like to tell all students that they should definitely give Cramkey Dumps a try.
Maja Aug 30, 2024
That sounds great. I'll definitely check them out. Thanks for the suggestion!
Ella-Rose
Amazing website with excellent Dumps. I passed my exam and secured excellent marks!!!
Alisha Aug 17, 2024
Extremely accurate. They constantly update their materials with the latest exam questions and answers, so you can be confident that what you're studying is up-to-date.
Question 23

The Plan Stakeholder Management process belongs to which Process Group?

Options:

A.

Executing

B.

Initiating

C.

Planning

D.

Monitoring and Controlling

Discussion
Page: 5 / 26
Title
Questions
Posted

PMI-100
PDF

$42  $104.99

PMI-100 Testing Engine

$50  $124.99

PMI-100 PDF + Testing Engine

$66  $164.99