Question 24

What cost estimating approach uses the work breakdown structure to create a cost estimate?

Options:

A.

Analogous

B.

Definitive

C.

Top down

D.

Parametric

Discussion
Ivan
I tried these dumps for my recent certification exam and I found it pretty helpful.
Elis Jul 26, 2026
Agree!!! The questions in the dumps were quite similar to what came up in the actual exam. It gave me a good idea of the types of questions to expect and helped me revise efficiently.
Alaia
These Dumps are amazing! I used them to study for my recent exam and I passed with flying colors. The information in the dumps is so valid and up-to-date. Thanks a lot!!!
Zofia Jul 11, 2026
That's great to hear! I've been struggling to find good study material for my exam. I will ty it for sure.
Faye
Yayyyy. I passed my exam. I think all students give these dumps a try.
Emmeline Jul 22, 2026
Definitely! I have no doubt new students will find them to be just as helpful as I did.
Joey
I highly recommend Cramkey Dumps to anyone preparing for the certification exam. They have all the key information you need and the questions are very similar to what you'll see on the actual exam.
Dexter Jul 11, 2026
Agreed. It's definitely worth checking out if you're looking for a comprehensive and reliable study resource.
Yusra
I passed my exam. Cramkey Dumps provides detailed explanations for each question and answer, so you can understand the concepts better.
Alisha Jul 11, 2026
I recently used their dumps for the certification exam I took and I have to say, I was really impressed.
Question 25

Which of the following terms is used for a schedule compression technique where two activities that were previously scheduled to start sequentially start at the same time?

Options:

A.

Fast tracking

B.

Compressing

C.

Float

D.

Crashing

Discussion
Question 26

You are the program manager of HYH Program for your organization. Your program is to create a new sports arena for your city within 12 months. Your program has seven projects and you've worked with all of the project managers before. Even though you've worked with the project managers before you still need to define the authority of the project managers and their projects. What document names the project manager for the project?

Options:

A.

Project charter for each project

B.

Program human resource management plan

C.

Project scope statement

D.

Program management charter

Discussion
Question 27

Part of your job as the program manager is to coach the project managers on their duties and goals. One of the project managers, Holly, is having trouble discerning the difference between quality assurance and quality control. She understands that she needs both to help you reach the program goals. Which statement best describes quality assurance for a project within your program?

Options:

A.

Quality assurance is an inspection-driven process to keep mistakes out of the project.

B.

Quality assurance is a prevention-driven process to keep mistakes out of the project.

C.

Quality assurance defines quality and sets goals for the project team.

D.

Quality assurance is an organization-wide process to do the work according the organizational goals and metrics.

Discussion