Question 24

What cost estimating approach uses the work breakdown structure to create a cost estimate?

Options:

A.

Analogous

B.

Definitive

C.

Top down

D.

Parametric

Discussion
Mylo
Excellent dumps with authentic information… I passed my exam with brilliant score.
Dominik Mar 14, 2026
That's amazing! I've been looking for good study material that will help me prepare for my upcoming certification exam. Now, I will try it.
Rosalie
I passed. I would like to tell all students that they should definitely give Cramkey Dumps a try.
Maja Mar 4, 2026
That sounds great. I'll definitely check them out. Thanks for the suggestion!
Sam
Can I get help from these dumps and their support team for preparing my exam?
Audrey Mar 10, 2026
Definitely, you won't regret it. They've helped so many people pass their exams and I'm sure they'll help you too. Good luck with your studies!
Ivan
I tried these dumps for my recent certification exam and I found it pretty helpful.
Elis Mar 14, 2026
Agree!!! The questions in the dumps were quite similar to what came up in the actual exam. It gave me a good idea of the types of questions to expect and helped me revise efficiently.
Question 25

Which of the following terms is used for a schedule compression technique where two activities that were previously scheduled to start sequentially start at the same time?

Options:

A.

Fast tracking

B.

Compressing

C.

Float

D.

Crashing

Discussion
Question 26

You are the program manager of HYH Program for your organization. Your program is to create a new sports arena for your city within 12 months. Your program has seven projects and you've worked with all of the project managers before. Even though you've worked with the project managers before you still need to define the authority of the project managers and their projects. What document names the project manager for the project?

Options:

A.

Project charter for each project

B.

Program human resource management plan

C.

Project scope statement

D.

Program management charter

Discussion
Question 27

Part of your job as the program manager is to coach the project managers on their duties and goals. One of the project managers, Holly, is having trouble discerning the difference between quality assurance and quality control. She understands that she needs both to help you reach the program goals. Which statement best describes quality assurance for a project within your program?

Options:

A.

Quality assurance is an inspection-driven process to keep mistakes out of the project.

B.

Quality assurance is a prevention-driven process to keep mistakes out of the project.

C.

Quality assurance defines quality and sets goals for the project team.

D.

Quality assurance is an organization-wide process to do the work according the organizational goals and metrics.

Discussion