Question 24

What cost estimating approach uses the work breakdown structure to create a cost estimate?

Options:

A.

Analogous

B.

Definitive

C.

Top down

D.

Parametric

Discussion
Honey
I highly recommend it. They made a big difference for me and I'm sure they'll help you too. Just make sure to use them wisely and not solely rely on them. They should be used as a supplement to your regular studies.
Antoni Oct 25, 2024
Good point. Thanks for the advice. I'll definitely keep that in mind.
Peyton
Hey guys. Guess what? I passed my exam. Thanks a lot Cramkey, your provided information was relevant and reliable.
Coby Sep 6, 2024
Thanks for sharing your experience. I think I'll give Cramkey a try for my next exam.
Ayesha
They are study materials that are designed to help students prepare for exams and certification tests. They are basically a collection of questions and answers that are likely to appear on the test.
Ayden Oct 16, 2024
That sounds interesting. Why are they useful? Planning this week, hopefully help me. Can you give me PDF if you have ?
Josie
I just passed my certification exam using their dumps and I must say, I was thoroughly impressed.
Fatimah Oct 24, 2024
You’re right. The dumps were authentic and covered all the important topics. I felt confident going into the exam and it paid off.
Question 25

Which of the following terms is used for a schedule compression technique where two activities that were previously scheduled to start sequentially start at the same time?

Options:

A.

Fast tracking

B.

Compressing

C.

Float

D.

Crashing

Discussion
Question 26

You are the program manager of HYH Program for your organization. Your program is to create a new sports arena for your city within 12 months. Your program has seven projects and you've worked with all of the project managers before. Even though you've worked with the project managers before you still need to define the authority of the project managers and their projects. What document names the project manager for the project?

Options:

A.

Project charter for each project

B.

Program human resource management plan

C.

Project scope statement

D.

Program management charter

Discussion
Question 27

Part of your job as the program manager is to coach the project managers on their duties and goals. One of the project managers, Holly, is having trouble discerning the difference between quality assurance and quality control. She understands that she needs both to help you reach the program goals. Which statement best describes quality assurance for a project within your program?

Options:

A.

Quality assurance is an inspection-driven process to keep mistakes out of the project.

B.

Quality assurance is a prevention-driven process to keep mistakes out of the project.

C.

Quality assurance defines quality and sets goals for the project team.

D.

Quality assurance is an organization-wide process to do the work according the organizational goals and metrics.

Discussion