New Year Special 75% Discount offer - Ends in 0d 00h 00m 00s - Coupon code: 75brite

PMI Updated PgMP Exam Questions and Answers by azalea

Page: 5 / 16

PMI PgMP Exam Overview :

Exam Name: Program Management Professional (PgMP)
Exam Code: PgMP Dumps
Vendor: PMI Certification: PMI Certification
Questions: 452 Q&A's Shared By: azalea
Question 20

You have created a control chart for a repeatable process in your program. You have discovered that the seven most recent measurements are all on the positive side of the mean in your control chart. What is this phenomenon called?

Options:

A.

Rule of Improvement

B.

Mean Improvement

C.

Rule of Seven

D.

Low-Riding Mean

Discussion
Zayaan
Successfully aced the exam… Thanks a lot for providing amazing Exam Dumps.
Harmony Dec 15, 2025
That's fantastic! I'm glad to hear that their dumps helped you. I also used them and found it accurate.
Josie
I just passed my certification exam using their dumps and I must say, I was thoroughly impressed.
Fatimah Dec 18, 2025
You’re right. The dumps were authentic and covered all the important topics. I felt confident going into the exam and it paid off.
Ella-Rose
Amazing website with excellent Dumps. I passed my exam and secured excellent marks!!!
Alisha Dec 15, 2025
Extremely accurate. They constantly update their materials with the latest exam questions and answers, so you can be confident that what you're studying is up-to-date.
Pippa
I was so happy to see that almost all the questions on the exam were exactly what I found in their Dumps.
Anastasia Dec 21, 2025
You are right…It was amazing! The Cramkey Dumps were so comprehensive and well-organized, it made studying for the exam a breeze.
Question 21

A multiyear program is ready to conclude. It has achieved all business objectives and is delivering its intended benefits. However, the program sponsor is not willing to sign the formal program closure acceptance document and the program continues to incur operational costs.

What should the program manager do next?

Options:

A.

Ask the finance department to increase the program budget

B.

Escalate the issue to the program governance board

C.

Ask key stakeholders to influence the program sponsor

D.

Direct component project managers to archive all relevant project documents

Discussion
Question 22

Who owns the program?

Options:

A.

Program manager

B.

Project manager

C.

Program director

D.

Program sponsor

Discussion
Question 23

A sponsor decides that the business environment is unfavorable for continuation of a program. The sponsor asks that the program be closed.

What items should be completed as part of the program’s final report?

Options:

A.

Lessons learned, successes and failures, and financial and performance assessments

B.

Final updates to the benefits register, successes and failures, and resource disposition

C.

Financial and performance assessments, successes and failures, and reason(s) for program closure

D.

Knowledge transition, successes and failures, and reason(s) for program closure

Discussion
Page: 5 / 16

PgMP
PDF

$26.25  $104.99

PgMP Testing Engine

$31.25  $124.99

PgMP PDF + Testing Engine

$41.25  $164.99