Question 12

Which of the following is NOT true regarding the program work breakdown structure (WBS)?

Options:

A.

It defines a program and groups the program's discrete work elements in a way that helps organize and define the total work scope of the program.

B.

It subdivides the program deliverables to work packages that are linked to the activities within the program.

C.

It defines all the work and only the required work for the program.

D.

It subdivides the program deliverables to work packages that are linked to the activities within the program.

Discussion
Question 13

A program manager initiates a new global program to create a higher level of protection for a company's intellectual property. The company exhibits a relaxed culture and environment, and is intolerant of processes to the point of being considered process-adverse. However, the company's culture is tolerant of long-term program activities, provided there is continuous progress on improving the protection of its intellectual property. Expectations for rapid progress are low.

What should the program manager do next?

Options:

A.

Tailor program sponsor and stakeholder engagement and communications activities to meet the company's expectations

B.

Insist on maintaining a set of tightly controlled stakeholder register and engagement plan documents to meet expectations

C.

Provide detailed information to the most influential program sponsors and stakeholders

D.

Ensure that the component stakeholders have the appropriate level of communications required to meet their needs

Discussion
Question 14

You are the program manager for your organization. You're currently working with the program director, Nancy Holmes, to define a new program and the benefits the program should create. Of the following, which is the best definition of a benefit a program creates?

Options:

A.

A benefit is an outcome of the constituent projects within a program.

B.

A benefit is a project and program deliverables that the organization may use immediately.

C.

A benefit is a deliverable of a program or project that is worth more than the cost to create the deliverable.

D.

A benefit is an outcome of actions and behaviors that provides utility to stakeholders.

Discussion
Fatima
Hey I passed my exam. The world needs to know about it. I have never seen real exam questions on any other exam preparation resource like I saw on Cramkey Dumps.
Niamh Sep 2, 2025
That's true. Cramkey Dumps are simply the best when it comes to preparing for the certification exam. They have all the key information you need and the questions are very similar to what you'll see on the actual exam.
Victoria
Hey, guess what? I passed the certification exam! I couldn't have done it without Cramkey Dumps.
Isabel Sep 18, 2025
Same here! I was so surprised when I saw that almost all the questions on the exam were exactly what I found in their study materials.
Sarah
Yeah, I was so relieved when I saw that the question appeared in the exam were similar to their exam dumps. It made the exam a lot easier and I felt confident going into it.
Aaliyah Sep 2, 2025
Same here. I've heard mixed reviews about using exam dumps, but for us, it definitely paid off.
Kylo
What makes Cramkey Dumps so reliable? Please guide.
Sami Sep 23, 2025
Well, for starters, they have a team of experts who are constantly updating their material to reflect the latest changes in the industry. Plus, they have a huge database of questions and answers, which makes it easy to study and prepare for the exam.
Nadia
Why these dumps are important? Can I pass my exam without these dumps?
Julian Sep 3, 2025
The questions in the Cramkey dumps are explained in detail and there are also study notes and reference materials provided. This made it easier for me to understand the concepts and retain the information better.
Question 15

You are the program manager of the YGH Program. A vendor has recently completed his contracted work for your program. You agree that the vendor has completed the procured work so what document should you and the vendors now sign?

Options:

A.

Certificate of completion

B.

Proposal agreement

C.

Invoice

D.

Contract

Discussion