New Year Sale Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: get65

PMI Updated PMI-RMP Exam Questions and Answers by tomos

Page: 2 / 19

PMI PMI-RMP Exam Overview :

Exam Name: PMI Risk Management Professional (PMI-RMP) Exam
Exam Code: PMI-RMP Dumps
Vendor: PMI Certification: PMI Certification
Questions: 264 Q&A's Shared By: tomos
Question 8

The scope of a large mobile network deployment project includes equipment to be furnished by the customer. The risk manager is concerned that the equipment delivery might be delayed, causing additional delays in the project.

What should the risk manager do?

Options:

A.

Follow up on the schedule and assess the best course of action if any delays are detected.

B.

Ensure the equipment constraint is well-documented and manage it as a high-impact project risk.

C.

Raise the issue with the project sponsor so it can be handled as a sales or contractual matter.

D.

Obtain a signed commitment from the customer that equipment will be delivered on time. 

Discussion
Anaya
I found so many of the same questions on the real exam that I had already seen in the Cramkey Dumps. Thank you so much for making exam so easy for me. I passed it successfully!!!
Nina Nov 14, 2025
It's true! I felt so much more confident going into the exam because I had already seen and understood the questions.
Amy
I passed my exam and found your dumps 100% relevant to the actual exam.
Lacey Nov 9, 2025
Yeah, definitely. I experienced the same.
Billy
It was like deja vu! I was confident going into the exam because I had already seen those questions before.
Vincent Nov 16, 2025
Definitely. And the best part is, I passed! I feel like all that hard work and preparation paid off. Cramkey is the best resource for all students!!!
Syeda
I passed, Thank you Cramkey for your precious Dumps.
Stella Nov 7, 2025
That's great. I think I'll give Cramkey Dumps a try.
Question 9

During a project team meeting, a risk manager realizes that the initial assumptions on the project schedule are too optimistic. The risk manager believes that the project might not meet its deadline as initially stated.

What is the reason for misunderstanding the assumptions from the beginning?

Options:

A.

Government regulations have changed in the last week, and now additional approval processes are required.

B.

The team's compensation was reduced and they lost the motivation to comply with the project deadline.

C.

The stakeholders prepared the initial schedule assumptions based only on the results of the last project.

D.

The sponsor had neither presented the actual results to the stakeholders nor updated the initial assumptions.

Discussion
Question 10

A company manages confidential customer information, and a data breach exposing sensitive information was discovered. What should the risk manager do?

Options:

A.

Execute the security risks contingency plan.

B.

Get a report of customers affected by the risk.

C.

Identify residual and secondary risks.

D.

Coordinate a response with the risk owner.

Discussion
Question 11

A project manager for a predictive project just received a scope change request where additional development is required. What should the risk manager do to support the project manager with this scope change request?

Options:

A.

Evaluate any new risks that are introduced due to the change in scope.

B.

Update the risk management plan to reflect the scope change.

C.

Reassess the identified risks that impact the project scope.

D.

Update the risk register to identify, analyze, and plan a response for any new risk.

Discussion
Page: 2 / 19
Title
Questions
Posted

PMI-RMP
PDF

$36.75  $104.99

PMI-RMP Testing Engine

$43.75  $124.99

PMI-RMP PDF + Testing Engine

$57.75  $164.99