Month End Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: cram70off

PMI Updated PMI-RMP Exam Questions and Answers by kareem

Page: 3 / 19

PMI PMI-RMP Exam Overview :

Exam Name: PMI Risk Management Professional (PMI-RMP) Exam
Exam Code: PMI-RMP Dumps
Vendor: PMI Certification: PMI Certification
Questions: 264 Q&A's Shared By: kareem
Question 12

During the construction of a housing development, a project team realizes they exceeded their materials budget during the first of three execution stages. The risk manager observed that the team did not notice that the cost of the materials increased due to continuous inflation in the steel market.

What could have been done during project planning to avoid overspending?

Options:

A.

Met weekly with the finance team to monitor the cost

B.

Communicated with the stakeholders that the project costs might increase

C.

Properly documented the triggers and actions for the risk

D.

Engaged with the sponsor to buy the steel in advance of the project 

Discussion
Question 13

Stakeholder deliverable reviews will start soon and additional work is expected to resolve any issues or required adjustments. Budget overruns during execution have put serious constraints on the remainder of the project's budget.

What should the project manager do next?

Options:

A.

Request a budget relief using the management reserve.

B.

Conduct a risk reassessment and reserve analysis.

C.

Review the consequences of potential changes.

D.

Coach stakeholders on risk identification practices.

Discussion
Question 14

Some project risks are applicable for the project's lifecycle while others risks are only applicable to specific project activities. When should project risks be closed?

Options:

A.

When the forecast activity date has been met or exceeded

B.

When the stakeholders agree a risk is no longer applicable

C.

When the risk has been realized and can no longer happen again

D.

When iterative data analysis determines the risk is not applicable

Discussion
Zayaan
Successfully aced the exam… Thanks a lot for providing amazing Exam Dumps.
Harmony Dec 15, 2025
That's fantastic! I'm glad to hear that their dumps helped you. I also used them and found it accurate.
Inaya
Passed the exam. questions are valid. The customer support is top-notch. They were quick to respond to any questions I had and provided me with all the information I needed.
Cillian Dec 22, 2025
That's a big plus. I've used other dump providers in the past and the customer support was often lacking.
Conor
I recently used these dumps for my exam and I must say, I was impressed with their authentic material.
Yunus Dec 28, 2025
Exactly…….The information in the dumps is so authentic and up-to-date. Plus, the questions are very similar to what you'll see on the actual exam. I felt confident going into the exam because I had studied using Cramkey Dumps.
Freddy
I passed my exam with flying colors and I'm confident who will try it surely ace the exam.
Aleksander Dec 6, 2025
Thanks for the recommendation! I'll check it out.
Honey
I highly recommend it. They made a big difference for me and I'm sure they'll help you too. Just make sure to use them wisely and not solely rely on them. They should be used as a supplement to your regular studies.
Antoni Dec 10, 2025
Good point. Thanks for the advice. I'll definitely keep that in mind.
Question 15

The project director and project manager have met with the board and determined that the project has depleted the entire contingency reserve and has started eroding the profit margin.

The project manager would like the risk manager to take full advantage of opportunities.

Which response should the risk manager take?

Options:

A.

Mitigate

B.

Accept

C.

Transfer

D.

Exploit

Discussion
Page: 3 / 19
Title
Questions
Posted

PMI-RMP
PDF

$31.5  $104.99

PMI-RMP Testing Engine

$37.5  $124.99

PMI-RMP PDF + Testing Engine

$49.5  $164.99