Exam Name: | PMI Risk Management Professional (PMI-RMP) Exam | ||
Exam Code: | PMI-RMP Dumps | ||
Vendor: | PMI | Certification: | PMI Certification |
Questions: | 264 Q&A's | Shared By: | ayzal |
A project team has completed the risk identification steps in a project and compiled a list of 25 risks. The team wants to create response plans for all the risks to avoid any future issues, but the resources and constraints limit the options.
What should the risk manager do?
The project team is updating the risk register with the minimum acceptable level of exposure and impact for each risk. The team also wants to determine if they have reached the maximum level of exposure before they escalate the risk.
What should the team perform in this scenario?
A project team's manager is responsible for delivering a specific initiative for the organization. They are preparing for a monthly meeting where the manager will present on the current state of this initiative. The agile project lead sends the manager the following email with the current initiative status (Refer to the email exhibit).
How many total story points is the entire initiative?
A list of risks was identified that could occur during the design phase. Now, the team finished the design phase and those risks did not materialize.
What should the project manager do next?