Month End Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: cram70off

PMI Updated PMI-RMP Exam Questions and Answers by laurie

Page: 11 / 19

PMI PMI-RMP Exam Overview :

Exam Name: PMI Risk Management Professional (PMI-RMP) Exam
Exam Code: PMI-RMP Dumps
Vendor: PMI Certification: PMI Certification
Questions: 264 Q&A's Shared By: laurie
Question 44

The risk manager of a major project needs to ensure the organizational process assets (OPAsj are updated as a result of risk management activities. How will the risk manager accomplish this?

Options:

A.

Ensuring that the project sponsor is kept well-informed

B.

Arranging periodic risk: management process audits

C.

Communicating the status of risks regularly to stakeholders

D.

Monitoring costs with intervention when necessary

Discussion
Question 45

A project team is leading a software development project. During the project kickoff meeting, the risk manager discovers that a vendor has not finalized the timeline for delivering an essential component. This creates uncertainty in the overall project schedule.

What should the risk manager do to address the risk?

Options:

A.

Hold a meeting to assess the risk's impact and create a response plan with alternative timelines.

B.

Adjust the overall project schedule based on assumptions about the vendor's timeline.

C.

Defer the risk discussion until the vendor finalizes the timeline to prioritize the project's start.

D.

Focus on internal risks and assume the vendor will resolve the issue independently.

Discussion
Question 46

A risk manager has been assigned to an upcoming project. A senior risk manager within the organization recently completed a similar project and has provided a lessons learned document to aid planning efforts for the upcoming project. Upon reviewing the document, the risk manager discovers that the completed project was delivered several months behind schedule and several thousands of dollars over budget. The root cause was determined to be an unforeseen risk trigger that caused several items to be reworked, creating cascading schedule delays and depleting management reserves.

What should the risk manager do to mitigate the chance of the same issues reoccurring?

Options:

A.

Ensure that all project stakeholders have a copy of and understand the project's risk management plan.

B.

Increase the management reserves and inform stakeholders of what is available to cover any unexpected expenses

C.

Distribute the lessons learned document to stakeholders knowing that the likelihood of reoccurrence is low.

D.

Document the known risk triggers as the identified cost and schedule risks in the risk register. 

Discussion
Alaya
Best Dumps among other dumps providers. I like it so much because of their authenticity.
Kaiden Dec 28, 2025
That's great. I've used other dump providers in the past and they were often outdated or had incorrect information. This time I will try it.
Walter
Yayyy!!! I passed my exam with the help of Cramkey Dumps. Highly appreciated!!!!
Angus Dec 24, 2025
YES….. I saw the same questions in the exam.
Fatima
Hey I passed my exam. The world needs to know about it. I have never seen real exam questions on any other exam preparation resource like I saw on Cramkey Dumps.
Niamh Dec 9, 2025
That's true. Cramkey Dumps are simply the best when it comes to preparing for the certification exam. They have all the key information you need and the questions are very similar to what you'll see on the actual exam.
Robin
Cramkey is highly recommended.
Jonah Dec 2, 2025
Definitely. If you're looking for a reliable and effective study resource, look no further than Cramkey Dumps. They're simply wonderful!
Question 47

A newly assigned risk manager realizes that a project has unrealistic funding and low resources. Which document should the risk manager review?

Options:

A.

Risk assessment criteria

B.

Project management plan

C.

Project assumptions

D.

Risk management plan 

Discussion
Page: 11 / 19
Title
Questions
Posted

PMI-RMP
PDF

$31.5  $104.99

PMI-RMP Testing Engine

$37.5  $124.99

PMI-RMP PDF + Testing Engine

$49.5  $164.99