Big Halloween Sale Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: get65

PMI Updated PMI-RMP Exam Questions and Answers by ronald

Page: 14 / 19

PMI PMI-RMP Exam Overview :

Exam Name: PMI Risk Management Professional (PMI-RMP) Exam
Exam Code: PMI-RMP Dumps
Vendor: PMI Certification: PMI Certification
Questions: 264 Q&A's Shared By: ronald
Question 56

The risk manager for a large-scale software development project with a tight deadline and multiple stakeholders highlights concerns about potential delays, communication gaps, and vendor reliability. During the early stages of the project, the project sponsor requests that the risk manager identify and address any potential risks that could disrupt project delivery.

What should the risk manager do?

Options:

A.

Create a list of potential issues.

B.

Consult the project management plan.

C.

Conduct risk management exercises.

D.

Perform qualitative risk analysis.

Discussion
Question 57

A risk management team has completed a quantitative analysis, and the individual score in terms of schedule and cost has been identified. The team is consolidating inputs for contingency planning and notices that the available time and funds are not sufficient for all the risks.

What should the risk manager advise the project team?

Options:

A.

Ask the project sponsor for more time and funds if needed.

B.

Create a change request if there are additional needs based on the risk responses.

C.

Accept some risks might not be materialized so no extra time and funds will be needed.

D.

Focus on the high-impact risk for contingency planning purposes.

Discussion
Question 58

During a project's planning phase, the project team identifies a potential supplier delay and marks it as a significant risk. A risk manager is tasked with effectively monitoring this risk.

What should the risk manager document as the risk trigger?

Options:

A.

The probability and impact rating of the supplier's delay on the project

B.

The response strategy, such as increasing inventory or finding an alternative supplier

C.

The specific event or condition, such as the supplier missing a delivery deadline

D.

The threshold for acceptable delay, such as a maximum of three days before impacting project milestones

Discussion
Question 59

A financial service firm adheres to heavily regulated compliance legislation. During the firm's latest project, the Chief Financial Officer (CFO) and the Chief Information Officer (CIO) endorsed a risk-based approach. This approach ensured compliance with the legislative requirements for properly storing confidential employee salary information. The risk manager recorded this information in the project's risk management plan.

What is the organization's risk maturity level?

Options:

A.

No maturity

B.

Low maturity

C.

Medium maturity

D.

High maturity

Discussion
Robin
Cramkey is highly recommended.
Jonah Sep 1, 2025
Definitely. If you're looking for a reliable and effective study resource, look no further than Cramkey Dumps. They're simply wonderful!
Elise
I've heard that Cramkey is one of the best websites for exam dumps. They have a high passing rate and the questions are always up-to-date. Is it true?
Cian Sep 22, 2025
Definitely. The dumps are constantly updated to reflect the latest changes in the certification exams. And I also appreciate how they provide explanations for the answers, so I could understand the reasoning behind each question.
Zayaan
Successfully aced the exam… Thanks a lot for providing amazing Exam Dumps.
Harmony Sep 16, 2025
That's fantastic! I'm glad to hear that their dumps helped you. I also used them and found it accurate.
Wyatt
Passed my exam… Thank you so much for your excellent Exam Dumps.
Arjun Sep 26, 2025
That sounds really useful. I'll definitely check it out.
Page: 14 / 19
Title
Questions
Posted

PMI-RMP
PDF

$36.75  $104.99

PMI-RMP Testing Engine

$43.75  $124.99

PMI-RMP PDF + Testing Engine

$57.75  $164.99