Big Halloween Sale Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: get65

PMI Updated PMI-RMP Exam Questions and Answers by serenity

Page: 4 / 19

PMI PMI-RMP Exam Overview :

Exam Name: PMI Risk Management Professional (PMI-RMP) Exam
Exam Code: PMI-RMP Dumps
Vendor: PMI Certification: PMI Certification
Questions: 264 Q&A's Shared By: serenity
Question 16

The project’s customer has stated the project must be completed by a date indicated as the P90 date established on the Monte Carlo analysis. What should the project manager do to ensure the P90 date is met?

Options:

A.

Update the assumptions/exclusions register

B.

Hire more resources and crash the schedule

C.

Perform a qualitative risk analysis for the project

D.

Mitigate risks identified on the sensitivity analysis

Discussion
Question 17

At the beginning of a small project, the risk manager facilitates workshops to identify and analyze risks. At the end of the sessions, a stakeholder says that there should be no need to meet again about the risk register now that it's complete since it is such a short and simple project.

How should the risk manager respond to this comment?

Options:

A.

The risk register must only be updated if a change is approved during the project.

B.

Agree on the condition that the risk register be updated if the project environment changes.

C.

Compromise by updating the risk register at the end of each phase only.

D.

Insist on continuous review and updating of the risk register during the project.

Discussion
Question 18

In a large industrial business, an on-going system development project faces a previously identified risk. The risk is adequately managed by the risk manager, however there is still residual risk.

What should the risk manager do?

Options:

A.

Update the risk register accordingly and review it in regular project meetings.

B.

Accept the risk because residual risks are often low.

C.

Ask a subject matter expert (SME) to assess the residual risk and take action.

D.

Assign a risk owner and set it as high priority and high impact.

Discussion
Carson
Yeah, definitely. I would definitely recommend Cramkey Dumps to anyone who is preparing for an exam.
Rufus Sep 9, 2025
Me too. They're a lifesaver!
Marley
Hey, I heard the good news. I passed the certification exam!
Jaxson Sep 11, 2025
Yes, I passed too! And I have to say, I couldn't have done it without Cramkey Dumps.
Amy
I passed my exam and found your dumps 100% relevant to the actual exam.
Lacey Sep 25, 2025
Yeah, definitely. I experienced the same.
Yusra
I passed my exam. Cramkey Dumps provides detailed explanations for each question and answer, so you can understand the concepts better.
Alisha Sep 13, 2025
I recently used their dumps for the certification exam I took and I have to say, I was really impressed.
Question 19

An experienced and the only developer on a software implementation project will be on leave for several weeks. The risk of this critical resource's availability was added to the risk register. Contingencies were made for a support developer to job shadow this resource, depending on how things go prior to their leave. The project team was pleased with the backup plan and the new resource was able to shadow for a few weeks.

What should the risk manager do next?

Options:

A.

Update the risk register to indicate the risk has occurred and close out the expired risk from the register.

B.

Update, continuously monitor, and communicate the residual and secondary risks of the backup resource on the project.

C.

Hire a permanent developer to support the project, and work with the backup resource to eliminate this risk.

D.

Hire another developer to support the project, contingent on when the experienced developer returns. 

Discussion
Page: 4 / 19
Title
Questions
Posted

PMI-RMP
PDF

$36.75  $104.99

PMI-RMP Testing Engine

$43.75  $124.99

PMI-RMP PDF + Testing Engine

$57.75  $164.99