Month End Sale Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: get65

PMI Updated PMI-RMP Exam Questions and Answers by serenity

Page: 4 / 16

PMI PMI-RMP Exam Overview :

Exam Name: PMI Risk Management Professional (PMI-RMP) Exam
Exam Code: PMI-RMP Dumps
Vendor: PMI Certification: PMI Certification
Questions: 221 Q&A's Shared By: serenity
Question 16

The project risk manager on a large firm fixed priced (FFP) contract has an up-to-date risk register with accurate and detailed information. What should the project risk manager do next?

Options:

A.

Recommend the removal of risks to the project manager to reduce project risk exposure.

B.

Advise the client that the project has exhausted contingency.

C.

Quantify the risk exposure that exceeds project contingency.

D.

Generate reports to assess and communicate the project risk level.

Discussion
Amy
I passed my exam and found your dumps 100% relevant to the actual exam.
Lacey Aug 9, 2024
Yeah, definitely. I experienced the same.
Lennie
I passed my exam and achieved wonderful score, I highly recommend it.
Emelia Oct 2, 2024
I think I'll give Cramkey a try next time I take a certification exam. Thanks for the recommendation!
Hendrix
Great website with Great Exam Dumps. Just passed my exam today.
Luka Aug 31, 2024
Absolutely. Cramkey Dumps only provides the latest and most updated exam questions and answers.
Anaya
I found so many of the same questions on the real exam that I had already seen in the Cramkey Dumps. Thank you so much for making exam so easy for me. I passed it successfully!!!
Nina Oct 14, 2024
It's true! I felt so much more confident going into the exam because I had already seen and understood the questions.
Walter
Yayyy!!! I passed my exam with the help of Cramkey Dumps. Highly appreciated!!!!
Angus Nov 4, 2024
YES….. I saw the same questions in the exam.
Question 17

A project manager is working on a construction project. Based on past experience, the project manager identifies a risk that a supplier of a critical material may not deliver on time. The project manager has already accounted for this risk in the risk management plan. If this risk materializes, the project manager plans to procure the material from a different supplier. A potential risk in this plan is that there may be differences in the material provided by the first and second supplier.

What type of risk is this?

Options:

A.

Residual risk

B.

Primary risk

C.

Secondary risk

D.

Normal risk

Discussion
Question 18

The risk manager notices that in their workshops, most of the risks identified are threats. What should the risk manager do to increase the number of opportunities identified?

Options:

A.

Use the Delphi technique involving experts who have identified opportunities in the past

B.

Interview more stakeholders who have a positive mindset

C.

Conduct a strengths, weaknesses, opportunities, and threats (SWOT) analysis

D.

Conduct a political, economic, sociological, technological, legal, and environmental (PESTLE) analysis

Discussion
Question 19

The project manager has completed four projects all with similar scope. The project manager has recently been assigned to start on a new project and believes some risks may occur again on this project.

What should the project manager do?

Options:

A.

Implement the risk response strategies into the risk plan.

B.

Inform the sponsor that these risks should be added according to experience.

C.

Add the risks to the risk register and determine a contingency.

D.

Discuss and evaluate the identified risks with the project team.

Discussion
Page: 4 / 16

PMI-RMP
PDF

$36.75  $104.99

PMI-RMP Testing Engine

$43.75  $124.99

PMI-RMP PDF + Testing Engine

$57.75  $164.99