Halloween Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: cram70off

PMI Updated PMI-RMP Exam Questions and Answers by myah

Page: 16 / 21

PMI PMI-RMP Exam Overview :

Exam Name: PMI Risk Management Professional (PMI-RMP) Exam
Exam Code: PMI-RMP Dumps
Vendor: PMI Certification: PMI Certification
Questions: 333 Q&A's Shared By: myah
Question 64

A risk manager for a cross-functional project is initiating the risk identification process. The risk manager conducted some meetings for stakeholders to express their concerns, but some stakeholders are complaining that their opinions were not considered.

How should the risk manager address these concerns?

Options:

A.

Refer to the requirements documentation to confirm stakeholder requirements as they relate to risks.

B.

Refer to the project charter to find guidelines and stakeholder communication channels.

C.

Review the stakeholder register and stakeholder engagement plan to communicate and solicit stakeholder input.

D.

Rewrite the risk register to include the additional possible risks and inform the stakeholders.

Discussion
Inaya
Passed the exam. questions are valid. The customer support is top-notch. They were quick to respond to any questions I had and provided me with all the information I needed.
Cillian Sep 22, 2026
That's a big plus. I've used other dump providers in the past and the customer support was often lacking.
Nia
Why are these Dumps so important for students these days?
Mary Sep 27, 2026
With the constantly changing technology and advancements in the industry, it's important for students to have access to accurate and valid study material. Cramkey Dumps provide just that. They are constantly updated to reflect the latest changes and ensure that the information is up-to-date.
Esmae
I highly recommend Cramkey Dumps to anyone preparing for the certification exam.
Mollie Sep 15, 2026
Absolutely. They really make it easier to study and retain all the important information. I'm so glad I found Cramkey Dumps.
Freddy
I passed my exam with flying colors and I'm confident who will try it surely ace the exam.
Aleksander Sep 1, 2026
Thanks for the recommendation! I'll check it out.
Question 65

A certain risk is identified for a major project, and the risk response is planned. However, the analysis reveals a high probability for a secondary risk which will be tolerated based on the organization ' s risk thresholds. The secondary risk is subsequently registered. During project execution, the primary risk occurs, the planned action is taken, and the secondary risk emerges

What two actions should the risk owner take? (Choose two.)

Options:

A.

Implement the secondary risk response and update the project documents.

B.

Conduct meeting with all stakeholder to agree on post impact solutions.

C.

Set the corresponding trigger conditions to the secondary risk.

D.

Engage the project manager to authorize the secondary risk ' s response.

E.

Update and communicate assessments of the secondary risk ' s impact.

Discussion
Question 66

A risk manager is working on the risk management plan for a new digital platform and realizes the project sponsor, who is the IT manager, has not been invited to the project team meetings. The IT manager is concerned that the IT infrastructure is unable to host the new platform the team is creating. The risk manager asks the IT manager to be included in the meetings.

What should the IT manager ' s role be in the project team meetings?

Options:

A.

The IT manager should be included as a risk owner.

B.

The IT manager should refine the project baseline plans.

C.

The IT manager should be added as a project sponsor.

D.

The IT manager should lead the infrastructure execution.

Discussion
Question 67

There is a debate within the organization on whether projects need to be agile or waterfall. Some agile terms and principles are understood differently by the key stakeholders, and this delays the decision-making process.

Options:

A.

Organize training sessions to create awareness around the agile values for stakeholders.

B.

Facilitate a face-to-face discussion and have stakeholders agree to shift to agile for future projects.

C.

Recommend an external facilitator as no one in the organization is able to eliminate this roadblock.

D.

Allow stakeholders to discuss without the scrum master ' s intervention.

Discussion
Page: 16 / 21
Title
Questions
Posted

PMI-RMP
PDF

$31.5  $104.99

PMI-RMP Testing Engine

$37.5  $124.99

PMI-RMP PDF + Testing Engine

$49.5  $164.99