Question 44

Which process provides information for the project board to review an updated project plan?

Options:

A.

Initiating a project

B.

Controlling a stage

C.

Directing a project

D.

Managing a stage boundary

Discussion
Marley
Hey, I heard the good news. I passed the certification exam!
Jaxson Mar 25, 2026
Yes, I passed too! And I have to say, I couldn't have done it without Cramkey Dumps.
Syeda
I passed, Thank you Cramkey for your precious Dumps.
Stella Mar 17, 2026
That's great. I think I'll give Cramkey Dumps a try.
Josephine
I want to ask about their study material and Customer support? Can anybody guide me?
Zayd Mar 19, 2026
Yes, the dumps or study material provided by them are authentic and up to date. They have a dedicated team to assist students and make sure they have a positive experience.
Ivan
I tried these dumps for my recent certification exam and I found it pretty helpful.
Elis Mar 14, 2026
Agree!!! The questions in the dumps were quite similar to what came up in the actual exam. It gave me a good idea of the types of questions to expect and helped me revise efficiently.
Question 45

According to the ‘continued business justification’ principle, what should happen to the funds when a project can no longer be justified?

Options:

A.

They should be returned to corporate, programme management or customer

B.

They should be used to create an alternative business case for the project

C.

They should be transferred back to the project board to reassign

D.

They should be used to deliver a reduction in the scope of the project

Discussion
Question 46

Which is a purpose of the 'controlling a stage' process?

Options:

A.

To review the success of the project at the end of a management stage

B.

To agree work package acceptance and delivery requirements

C.

To produce regular highlight reports for the project board

D.

To re-plan the current stage and the project when requested

Discussion
Question 47

According to the 'continued business justification' principle, when is a justifiable reason for a project FIRST needed?

Options:

A.

After the executive has been appointed

B.

When authorized by the corporate, programme management or the customer

C.

Before work to start the project commences

D.

When an organization produces its business plans

Discussion
Page: 11 / 34
Title
Questions
Posted

Prince2-Foundation
PDF

$36.75  $104.99

Prince2-Foundation Testing Engine

$43.75  $124.99

Prince2-Foundation PDF + Testing Engine

$57.75  $164.99